TO BIDDERS OF RECORD November 16, 2016
Re:
File No. 3066.07
Addendum No. 1
Contract and Technical Documents
Spring 2017 Landfill Gas System Expansion (IFB0593-113016)
Four Hills Landfill
Nashua, New Hampshire
This Addendum shall be part of the Contract Documents for the above-referenced project.
Please acknowledge receipt of this Addendum in your bid for this project.
Responses to Questions from Bidders
1.
What are the depths of the existing wells which in which dewatering pumps will be
installed?
A: The attached Table A provides the depths for each of the wells.
What type of valves should be installed for the air and discharge lines shown on Detail 1
on Sheet 5 of the Construction Drawings?
A: Standard brass or high-density polyethylene (HDPE) ball valves are acceptable.
Detail 5 on Sheet3 shows geotextile over the top of the trench. Is the geotextile
required only on the top of the trench or on all sides?
A: The geotextile is required on the top of the trench only.
Is geotextile required below and above the draintube piping? If so, what type of
geotextile?
A: Nonwoven geotextile is part of the composite Draintube™ material.
On Detail 1 on Sheet 7, what is meant by “one roll width” shown at the top of the detail?
A: It signifies one roll width of Draintube™. Each roll is approximately 13 feet wide.
Will any seeding or re-vegetation be required?
A: The Contractor will not be responsible for seeding or re-vegetation.
Can you provide the name and contact of the surveyor the landfill uses on-site?
SANBORN, HEAD & ASSOCIATES, INC. www.sanbornhead.com