Finance Committee - Agenda - 3/6/2019 - P824
Payment:
The accepted quantity of sewer line connections to existing manholes shall be
paid for at the contract unit price under ITEM 8, and shall be full compensation
for modifications to the pipe to manhole joint to form a watertight connection,
by-pass pumping, decanting and disposal of debris at the City landfill and all
labor, tools and any other equipment necessary to complete the work as
specified in these Specifications and as directed by the Engineer.
I. REMOVE ABANDONED DRAIN LATERAL COMPLETE IN PLACE
Measurement:
The quantity of abandoned drain lateral (only if not in other trench excavation)
to be removed under ITEM 9 will be measured complete-in-place by the
LINEAR FOOT, complete-in-place, as specified in these Specifications and as
directed by the Engineer.
Payment:
The accepted quantity of abandoned drain lateral to be removed shall be
paid for at the contract unit price under ITEM 9, and shall constitute full
compensation for removal and disposal of the existing drain line, complete
in place as indicated on the drawings and/or as specified, including
excavation, backfill, plugging the hole at the structure from which the pipe
was removed, filling pipeline void with suitable material, removal of
unsuitable materials at the City landfill and all labor, tools, and equipment
necessary to complete the work, and not specifically included for payment
under other items.
J. REMOVE AND REPLACE CATCH BASIN COMPLETE IN PLACE
Measurement:
The quantity of catch basins removed and replaced under ITEM 10 and will be
measured complete-in-place by the VERTICAL FOOT as measured from the
interior bottom of the structure (sump) to the top of the catch basin casting,
complete-in-place, as specified in these Specifications and as directed by the
Engineer.
Payment:
The accepted quantity of catch basins removed and replaced shall be paid
for at the contract unit price under ITEM 10, and shall constitute full
compensation for removal and disposal of the existing catch basin,
constructing new pre-cast catch basin, furnishing and installing specified
frame and grate, furnishing and installing the specified oil/water separator
(The Eliminator®) and all necessary couplings and fittings, complete in
place as indicated on the drawings and/or as specified, including furnishing
all materials, labor, tools, and equipment necessary to complete the work,
including but not limited to excavation, backfill, catch basin bedding,
removal of unsuitable materials at the City landfill, catch basin vacuum
2019 Sewer Replacement Project Measurement and Payment
Nashua, NH 01150-5