C.
2.05
A.
MAINTENANCE OF TRAFFIC
Measurement:
Maintenance of traffic shall be measured as a LUMP SUM as specified herein.
Payment:
The contract price for Item 27 shall constitute full compensation for providing
and maintaining safe and passable traffic accommodations for public travel,
preventing dust nuisance and furnishing, erecting and maintaining necessary
traffic signs, barricades, lights, signals, flashing beacons, delineators and other
traffic control warning devices and shall include means of guidance of traffic
through and around the work zones. Traffic warning signs and other regulating
devices shall be installed in accordance with the MUTCD and details on the
plans. Payments toward the lump sum will be made at each payment
requisition based on the percent of contract completed and the balance will be
paid at final payment upon completion of all project requirements. Should the
contract be terminated prior to completion, or the contract work not completed,
total payment for this item shall be proportional to the percentage of the
contract completed.
UNANTICIPATED HAZARDOUS MATERIALS
ALLOWANCE FOR UNANTICIPATED HAZARDOUS MATERIALS
Measurement & Payment
ITEM 28 is intended to be a contingency pay item to be used in the event that
unanticipated hazardous material is encountered during the work.
Compensation shall only be paid to the Contractor if unanticipated hazardous
material is encountered and expenditure of the allowance, or portion of the
allowance, is authorized by the Engineer.
An allowance value has been established on the bid form for this item as a
means to include funds in the event that the Contractor is directed to perform
work associated with addressing unanticipated hazardous materials.
Costs for these pay items shall be negotiated between the Engineer and the
Contractor in accordance with provisions for changes in the work in the
General Conditions.
END OF SECTION
2019 Sewer Replacement Project Measurement and Payment
Nashua, NH 01150 - 12