Finance Committee - Agenda - 5/19/2021 - P35
Item No. 1 - Newton Conduit Extension
Change in Service Location- Newton Pump Station-Sub M/U
Date:
Description: Change in Service Location- Newton Pump Station-Sub M/U
Duration : 1 Shift/Shifts
A LABOR #men Hours Rate/Hour Shifts Total
Foreman-Jim 1 $ 70.82 1 $ -
O/T 1 $ 106.23 1 $ -
Operator 1-Norman 1 $ 53.73 1 $ -
O/T $ 80.60 1 $ -
Lab 3-Brandon 1 $ 57.54 1 $ -
O/T $ 86.31 1 $
Truck Drv-Tom 1 $ 54.02 1 $ -
O/T $ 81.03 1 $ -
Lab 1- Barry 1 $ 57.54 1 $ -
O/T $ 86.31 1 $ -
Lab 2- Pablo 1 $ 57,54 1 $ -
O/T $ 86.31 1 $ -
Labor subtotat [$e]
B: LABOR BENEFITS #men Hours Rate/Hour Shifts
Foreman-Jim 1 0 $ - 1 $ -
Operator 1-Norman 1 0 $ 29.86 1 $ -
Lab 3-Brandon 1 0 $ 28.76 1 $ -
Truck Drv-Tom 1 0 $ - 1 $ -
Lab 1- Barry 1 0 $ - 1 $ -
Lab 2- Pablo 1 0 $ - 1 $ :
subtotal Fringes[$__]
C: Material Qty. Unit Unit Cost
$ -
$ -
$ -
$ -
$ -
Subtotal Material:
D: EQUIPMENT Qty Hours Rate/Hour Shifts
Cat 345 Exc 1 $105.00 1 $ -
Cat 950 Loader 1 $65.00 1 $ -
Skid Steer 1 $72.00 1 $ -
Yanmar 100 1 $72.00 1 $
4300 Gradall 1 $68.00 1 $ -
Generator 50KW 1 $15.00 1 $ -
Tri Axle 1 $90.00 1 $ -
Trailer-Lowbed 1 $125.00 1 $ -
Trailer-Dump 1 $125.00 1 $ -
Crew Truck 1 $12.50 1 $ -
Concrete Pump Truck 1 $975.00 1 $ -
Subtotal Equipment]
E: SUBCONTRACTORS Qty. Unit Unit Cost
Ell 1L8 $ 4,344.56 $ 4,344.56
$ -
$ -
$ -
$ -
Subcontractor Total] $ 4,344.56