Item No. 1 - Newton Conduit Extension
Cost Qty
Description / Rate /Hrs Workers Ext
, oo 162.00
2" PVC Conduit Fiber $3.79 FOOT - $613.98
35.00
Duct Bank Spacers $4.70 FOOT - $164.50
, 175.00
1" PVC PLC to Wet Well $0.46 FOOT - $80.50
Subcontractor $0.00 0.00 - $0.00
Breakout
Labor: $1,955.00
Gross Margin Percent @ 15%: $293.25
Material: $1,822.88
Gross Margin Percent @ 15%: $273.43
Total: $4,344.56
Reservation of Rights
This price does not include any amount for impacts such as interference, disruptions, rescheduling, changes in the
sequence of work, delays and/or associated acceleration. We expressly reserve the right to submit our request for
any of these items.
Signed By:
Dated: 5/15/2020