Finance Committee - Agenda - 10/3/2018 - P87
Summary
CHANGE IN CONTRACT PRICE:
Original Contract Price
$715,657.50
CHANGE IN CONTRACT TIMES:
Original Contract Times
Substantial completion: September 21, 2018
Ready for final payment: October 6, 2018
Net changes from previous Change Orders
$119,989.50
Net change from previous Change Orders
Substantial completion: December 16, 2018
Ready for final payment: December 31, 2018
Contract Price prior to this Change Order
$835,647.00
Contract Times prior to this Change Order
Substantial completion: December 16,2018 _
Ready for final payment: December 31, 2018
Net Increase (deerease} of this Change Order
$50,995.00
Net Increase fdeerease) of this Change Order
Substantial completion: 0 days
Ready for final payment: 6 days
Contract Price with all approved Change Orders
Contract Times with all approved Change Orders
$886,642.00 Substantial completion: December 16, 2018
Ready for final payment: December 31, 2018
RECOMMENDED: ACCEPTED: APPROVED:
By: By BY. ee
DPW Contractor Mayor Jim Donchess
Engineer Owner
(Authorized Signature) (Authorized Signature) (Authorized Signature)
Date. Date: Date:
Change Order # 2 2 of 2
2018 CIPP Lining