18-0646 M
September 10, 2018
e Monitor and report on batching procedures and document maierials batched into
the mix
e Gradation and Asphalt Content (1 test/750 tons)
e Drilled Core Bulk Specific Gravity — core sampled by contractor and provided to
S.W.COLE at the suppliers laboratory (1 test/750 tons)
e Theoretical Maximum Specific Gravity - sampled by contractor and provided to
S.W.COLE at the suppliers laboratory (1 test/750 tons)
If back-to-back days of plant testing services are not required at the HMA plant due to
the paving schedule, we anticipate that some of the drilled cores will be tested at our
laboratory and billed at the unit rates provided in our response to IFBO660-052418.
Additionally we ha
The project will be serviced from our Londonderry, New Hampshire office. Our project
manager will be Andrew Michaud and can be reached at 603-716-2111 or
Andrew.Michaud@swcole.com.
SCHEDULE
We anticipate that our services will likely be needed on a part-time, as scheduled basis.
We generally request 48 hours notice for scheduling of our services.
BUDGET AND COMPENSATION
S.W.COLE will charge for our services on a unit rate basis in accordance with
Attachment A. The estimated cost for our services is included in Attachment A-1.
For estimating purposes, we have assumed 60 days of plant testing and observation
services. When the contractor submits a construction schedule, recommend
reevaluating our estimate and make adjustments if necessary.
TERMS AND CONDITIONS
We understand that the City will prepare a formal contract or purchase order should we
be selected for these services.