Summary
CHANGE IN CONTRACT PRICE:
Original Contract Price
CHANGE IN CONTRACT TIMES:
Original Contract Times
$43,875
Substantial completion: October 15, 2018
Ready for final payment: October 31, 2018
Net changes from previous Change Orders
$0.00
Net change from previous Change Orders
Substantial completion: 0 calendar days
Ready for final payment: 0 calendar days
Contract Price prior to this Change Order
$43,875
Contract Times prior to this Change Order
Substantial completion: October 15, 2018
Ready for final payment: October 31, 2018
Net Increase (deerease} of this Change Order
$27,581
Net Increase (decrease) of this Change Order
Substantial completion: 244 calendar days
Ready for final payment: 244 calendar days
Contract Price with all approved Change Orders
Contract Times with all approved Change Orders
$71,456 Substantial completion: June 15, 2019
Ready for final payment: June 30, 2019
RECOMMENDED: ACCEPTED: APPROVED:
By: By: By:
DPW Contractor Mayor Jim Donchess
Engineer Owner
(Authorized Signature) (Authorized Signature) (Authorized Signature)
Date: Date: Date:
Change Order #1 2 of 2
2018 Asphalt Testing