Skip to main content

Main navigation

  • Documents
  • Search

User account menu

  • Log in
Home
Nashua City Data

Breadcrumb

  1. Home
  2. Finance Committee - Agenda - 10/3/2018 - P87

Finance Committee - Agenda - 10/3/2018 - P87

By dnadmin on Mon, 11/07/2022 - 11:27
Document Date
Fri, 09/28/2018 - 14:44
Meeting Description
Finance Committee
Document Type
Agenda
Meeting Date
Wed, 10/03/2018 - 00:00
Page Number
87
Image URL
https://nashuameetingsstorage.blob.core.windows.net/nm-docs-pages/fin_a__100320…

Summary

CHANGE IN CONTRACT PRICE:
Original Contract Price

$715,657.50

CHANGE IN CONTRACT TIMES:
Original Contract Times

Substantial completion: September 21, 2018
Ready for final payment: October 6, 2018

Net changes from previous Change Orders

$119,989.50

Net change from previous Change Orders

Substantial completion: December 16, 2018
Ready for final payment: December 31, 2018

Contract Price prior to this Change Order

$835,647.00

Contract Times prior to this Change Order

Substantial completion: December 16,2018 _
Ready for final payment: December 31, 2018

Net Increase (deerease} of this Change Order

$50,995.00

Net Increase fdeerease) of this Change Order

Substantial completion: 0 days
Ready for final payment: 6 days

Contract Price with all approved Change Orders

Contract Times with all approved Change Orders

$886,642.00 Substantial completion: December 16, 2018
Ready for final payment: December 31, 2018
RECOMMENDED: ACCEPTED: APPROVED:
By: By BY. ee
DPW Contractor Mayor Jim Donchess
Engineer Owner
(Authorized Signature) (Authorized Signature) (Authorized Signature)

Date. Date: Date:

Change Order # 2 2 of 2

2018 CIPP Lining