Finance Committee - Agenda - 5/17/2017 - P285
SECTION 01570
ENVIRONMENTAL PROTECTION
Description
Notification
Implementation
Areaof Construction Activity
Protection of Water Resources
Construction in Areas Designated as Wetlands on the Drawings
Protecting and Minimizing Exposed Areas
Location of Storage Areas
Protection of Landscape
10. Cleering and Grubbing
11. Dischargeof Dewatering Operations
12. Dust Control
13. Seperation and Replacement of Topsoil
14. Bded Straw
15. Silt Fence
1. Description
OAONDWABRWN >
A. The work covered by this section of the specifications consists of furnishing all labor,
materias, tools and equipment and performing al work required for the prevention of
environmental pollution during and as a result of construction operations under this
contract.
B. Therequirenents set forth in this section of the specifications apply to roadway
reconstruction areas, cross-country areas, river and stream crossings, and construction in and
adjacent to welands, unless otherwise specifically stated.
2. Notification
The Engineer will notify the Contractor in writing of any norm-compliance with the foregoing
provisions. The Contractor shall, after receipt of such notice immediately take corrective action.
Such notice when delivered to the Contractor or his authorized representative at the site of the
work, shal be deemed sufficient for the purpose. If the Contractor fals to act promptly, the
Engineer may order stoppage of all or part of the work until satisfactory corrective action has
been taken. No clam for an extension of time or for excess costs or damage incurred by the
Contractor as a result of time lost due to any stop work orders shall be made unless it was later
determined that the Contractor was in compliance.
01570-1