Finance Committee - Agenda - 6/7/2017 - P453
01310-1
SECTION 01310
CONSTRUCTION SCHEDULES
PART 1 - GENERAL
1.1 DESCRIPTION
A.
Work Included: Within ten (10) days after the effective date of the Agreement
between Owner and Contractor submit to the Engineer an estimated progress
schedule as specified herein.
Form of Schedules:
1. Narrative: Completely describe the construction methods to be employed.
2. Network Analysis System:
a. Provide a separate horizontal schedule line for each trade or operation
and show concurrent and preceding activities.
b. Present in chronological order the beginning of each trade or operation
showing duration and float time.
c. Scale: Identify key dates and allow space for updating and revision.
3. Mathematical Analysis:
a. A mathematical analysis shall accompany the network diagram. A
computer printout will be acceptable.
b. Information shall be included on activity numbers, duration, early start,
late start, etc. and float times.
Content of Schedules:
1. Provide complete sequence of construction by activity:
a. Shop Drawings, Project Data and Samples:
1) Submittal dates.
2) Dates reviewed copies will be required.
b. Decision dates for:
1) Products specified by allowances.
2) Selection of finishes.
c. Estimated product procurement and delivery dates.
d. Dates for beginning and completion of each element of construction.
2. Identify work of separate phases and logically grouped activities.
3. Show the projected percentage of completion for each item of work as of the
first day of each month.
4. Provide separate sub-schedules, if requested by the Engineer, showing
submittals, review times, procurement schedules, and delivery dates.
Updating:
1. Show all changes occurring since previous submission.
2. Indicate progress of each activity, show completion dates.
3. Include:
a. Major changes in scope.
b. Activities modified since previous updating.
c. Revised projections due to changes.
d. Other identifiable changes.