Project Number: 228730 WWTE SCADA Upgrades
Issue Date: August 2017 Nashua, NH

4. Schedule _of Submittals) Submit preliminary and final Schedule of
Submittals. Include all submittals specified in Contract, General and
Special Conditions, and other Specification sections.

a. Include description of each submittal, date by which each submittal
will be delivered to Engineer and Owner date by which each
submittal must be approved to maintain project schedule, and
relevant section reference.

Finance Committee - Agenda - 11/15/2017 - P263

By dnadmin on Mon, 11/07/2022 - 10:19
  • Read more about Finance Committee - Agenda - 11/15/2017 - P263

Project Number: 228730
Issue Date: August 2017

WWTE SCADA Upgrades
Nashua, NH

2) Photograph construction progress and submit monthly with
Payment Application during progress of Work.

3) Photograph all areas of the Project Site to document final
conditions and submit with Application for Final aPayment.

Finance Committee - Agenda - 11/15/2017 - P262

By dnadmin on Mon, 11/07/2022 - 10:19
  • Read more about Finance Committee - Agenda - 11/15/2017 - P262

Project Number: 228730
Issue Date: August 2017

WWTE SCADA Upgrades
Nashua, NH

8. Pre-installation Conference and Coordination Meetings

a.

When required, convene a pre-installation conference at Site before
commencing certain Work that requires coordination or has special
requirements or approvals or convene coordination meetings as may
be generally required.

Finance Committee - Agenda - 11/15/2017 - P261

By dnadmin on Mon, 11/07/2022 - 10:19
  • Read more about Finance Committee - Agenda - 11/15/2017 - P261

Project Number: 228730
Issue Date: August 2017

WWTE SCADA Upgrades
Nashua, NH

e Requirements for start-up

e Inspection and acceptance of equipment put into service during
construction period

e Access, laydown and coordination with others

Finance Committee - Agenda - 11/15/2017 - P260

By dnadmin on Mon, 11/07/2022 - 10:19
  • Read more about Finance Committee - Agenda - 11/15/2017 - P260

Project Number: 228730 WWTE SCADA Upgrades
Issue Date: August 2017 Nashua, NH

answering machine) or provide that a phone call will be returned within one
hour.

3. During periods of construction and testing keep Owner and Engineer
informed in writing with name, address, and telephone number of
Contractor's representative who will be responsible and available outside of
normal working hours for emergency repairs and the maintenance of safety
devices.

Finance Committee - Agenda - 11/15/2017 - P259

By dnadmin on Mon, 11/07/2022 - 10:19
  • Read more about Finance Committee - Agenda - 11/15/2017 - P259

Project Number: 228730 WWTE SCADA Upgrades
Issue Date: August 2017 Nashua, NH

1) Substitute items will be processed in accordance with
subparagraph 1.03.C.6 below.

2) Substitute items will not be considered when indicated or
implied on Shop Drawing or material and equipment data
submittals without separate written request, or when
acceptance will require revision to the Contract Documents.

D. Measurement and Payment Procedures

Finance Committee - Agenda - 11/15/2017 - P258

By dnadmin on Mon, 11/07/2022 - 10:19
  • Read more about Finance Committee - Agenda - 11/15/2017 - P258

Project Number: 228730
Issue Date: August 2017

WOODARD & CURRAN

WWTE SCADA Upgrades
Nashua, NH

1) Engineer or Owner to include a detailed description of a
proposed change with supplementary or revised Drawings
and Specifications, including a change in Contract Times
related to the change (with a stipulation for any overtime
work required) and the period of time during which the
requested price will be considered valid. Prepare and submit
an estimate within 15 days.

Finance Committee - Agenda - 11/15/2017 - P257

By dnadmin on Mon, 11/07/2022 - 10:19
  • Read more about Finance Committee - Agenda - 11/15/2017 - P257

Project Number: 228730 WWTE SCADA Upgrades
Issue Date: August 2017 Nashua, NH

PART 3 - EXECUTION

3.01 GENERAL
Project Identification
Progress Cleaning and Waste Removal

3.02 OVERALL EXECUTION REQUIREMENTS
Coordination
Record Documents

3.03 STARTUP, TESTING, AND COMMISSIONING
Spare Parts
Checkout and Starting Systems
Starting, Adjusting, and Balancing
Startup and Commissioning/Performance Testing

3.04 ATTACHMENTS

Finance Committee - Agenda - 11/15/2017 - P256

By dnadmin on Mon, 11/07/2022 - 10:19
  • Read more about Finance Committee - Agenda - 11/15/2017 - P256

Project Number: 228730 WWTE SCADA Upgrades
Issue Date: August 2017 Nashua, NH

SECTION 01 11 05
OVERALL GENERAL REQUIREMENTS

PART 1-— GENERAL
1.01 SUMMARY

Finance Committee - Agenda - 11/15/2017 - P255

By dnadmin on Mon, 11/07/2022 - 10:19
  • Read more about Finance Committee - Agenda - 11/15/2017 - P255

Project Number: 228730 WWTE SCADA Upgrades
Issue Date: August, 2017 Nashua, NH

1.04 COORDINATION AND SEQUENCING
A. Coordination

1. Ensure that facilities and wastewater system flows are maintained and
remain in service at all times unless otherwise approved.

a. Obtain written approval of Owner for shutdowns. Notify Engineer a
minimum of two weeks prior to any required shutdowns.

b. Prepare a Shutdown Plan for each requested shutdown indicating
what existing valves must be operated by Owner personnel during
the shutdown.