Skip to main content

Main navigation

  • Documents
  • Search

User account menu

  • Log in
Home
Nashua City Data

Breadcrumb

  1. Home
  2. Finance Committee - Agenda - 11/15/2017 - P256

Finance Committee - Agenda - 11/15/2017 - P256

By dnadmin on Mon, 11/07/2022 - 10:19
Document Date
Wed, 11/15/2017 - 00:00
Meeting Description
Finance Committee
Document Type
Agenda
Meeting Date
Wed, 11/15/2017 - 00:00
Page Number
256
Image URL
https://nashuameetingsstorage.blob.core.windows.net/nm-docs-pages/fin_a__111520…

Project Number: 228730 WWTE SCADA Upgrades
Issue Date: August 2017 Nashua, NH

SECTION 01 11 05
OVERALL GENERAL REQUIREMENTS

PART 1-— GENERAL
1.01 SUMMARY

A. This Section specifies the overall general requirements for execution of the Work,
supplements items in the General and Supplemental General Conditions, and
applies to all Specifications and Drawings, including: administrative and
procedural requirements (relating to the process of contract administration, and the
methods of communicating, controlling, and assuring quality); general execution
requirements; and startup/commissioning and performance testing.

B. Section Includes

1.02 PRICE AND PAYMENT PROCEDURES
Schedule of Values
Payment Procedures
Change Procedures
Measurement and Payment Procedures
Correlation of Submittals

1.03 ADMINISTRATIVE REQUIREMENTS
Project Management and Coordination; Meetings
Documentation of Progress
Submittal Procedures
Closeout Procedures

1.04 QUALITY REQUIREMENTS
Reference Standards and Regulatory Requirements
Qualifications

PART 2 - PRODUCTS

2.01 SOURCE QUALITY CONTROL
General
Independent Testing Agency Certification
Factory Testing

2.02 PRODUCT REQUIREMENTS
General
Transportation and Handling
Storage and Protection

OVERALL GENERAL REQUIREMENTS
WOODARD & CURRAN 01 11 05-1

Page Image
Finance Committee - Agenda - 11/15/2017 - P256

Footer menu

  • Contact