Project Number: 228730
Issue Date: August 2017
WWTE SCADA Upgrades
Nashua, NH
8. Pre-installation Conference and Coordination Meetings
a.
When required, convene a pre-installation conference at Site before
commencing certain Work that requires coordination or has special
requirements or approvals or convene coordination meetings as may
be generally required.
Attendance required by parties directly affecting, or affected by,
Work of the specific Specification section. Notify Owner and
Engineer 5 days in advance of pre-installation conference. Party
requesting general coordination meeting to notify other party.
Review conditions, preparation and procedures, and coordination
with related Work.
B. Documentation of Progress
1. Submit preliminary and final Progress Schedules.
a.
Show complete sequence of construction by activity, identifying
Work of separate stages and other logically grouped activities.
Indicate the early and late start, early and late finish, float dates, and
duration.
Indicate estimated percentage of completion for each item of Work
at each submission.
Indicate dates for fabrication, factory testing, delivery, shipping and
field testing, and material and equipment delivery dates, including
those furnished by Owner. Coordinate with Schedule of Submittals.
2. Submit revised Progress Schedule on monthly basis and with each
Application for Payment, identifying changes since previous version.
Coordinate content with Schedule of Values, if any.
3. Submit weekly Safety Reports signed by the responsible on-Site person.
4. Provide documentation of pre-construction conditions, construction
progress, and final conditions with photographs*. Identify date, time,
orientation and Project identification.
a.
WOODARD & CURRAN
Provide photographs PDF or JPG format, minimum 300 dpi quality
and a minimum resolution of 6.0 megapixels.
1) Photograph all areas of the Project Site in the presence of the
Engineer to establish a record of pre-construction conditions.
Ensure existing conditions of roadway surfaces, curbing,
berms, sidewalks, driveways, property bounds, landscaped
areas, abutters’ property and any other items that might be
affected by the Work are clearly recorded.
OVERALL GENERAL REQUIREMENTS
01 11 05-7