Project Number: 228730 WWTE SCADA Upgrades
Issue Date: August, 2017 Nashua, NH
1.04 COORDINATION AND SEQUENCING
A. Coordination
1. Ensure that facilities and wastewater system flows are maintained and
remain in service at all times unless otherwise approved.
a. Obtain written approval of Owner for shutdowns. Notify Engineer a
minimum of two weeks prior to any required shutdowns.
b. Prepare a Shutdown Plan for each requested shutdown indicating
what existing valves must be operated by Owner personnel during
the shutdown.
C. Coordinate Work with the Owner and provide public notice, as
required.
2. Maintain access to facilities for the Owner throughout the Project.
B. Sequence
1. Sequence Work to minimize shutdowns and reflect sequencing in the
construction schedule.
PART 2 PRODUCTS - NOT USED
PART 3 EXECUTION - NOT USED
END OF SECTION
SUMMARY OF WORK
WOODARD & CURRAN 01 11 00-2