Project Number: 228730 WWTE SCADA Upgrades
Issue Date: August 2017 Nashua, NH
4. Schedule _of Submittals) Submit preliminary and final Schedule of
Submittals. Include all submittals specified in Contract, General and
Special Conditions, and other Specification sections.
a. Include description of each submittal, date by which each submittal
will be delivered to Engineer and Owner date by which each
submittal must be approved to maintain project schedule, and
relevant section reference.
b. Allow 15-30 days from receipt of submittal/resubmittal for Engineer
review of submittals and possible resubmittal.
5. Shop Drawings and Samples: Submit 2 prints and electronic files in PDF
format by email in accordance with the Schedule of Submittals required in
subparagraph 1.03.C.4 above.
a. Complete the submittal transmittal form included as an attachment
to this Section as is indicated, numbering each submittal
consecutively. Assign resubmittals the same transmittal number as
the original with a suffix of a sequential letter to indicate the
resubmittal (e.g. the first resubmittal of submittal 25 would be
number 25A.) Include only those documents previously issued
under original transmittal number in resubmittals. Do not combine
new submittals with resubmittals.
b. Attach a transmittal form to each group of Shop Drawings,
manufacturer's literature, equipment data and Samples submitted.
Use a sufficient number of transmittal forms so that: items on a
single transmittal form pertain to the same equipment item,
specification section or element of Work; items on a single
transmittal form are either original submittals or the same number
resubmittal; and each Sample is listed on a separate transmittal form.
Data shown on the Shop Drawings shall be complete with respect to
quantities, dimensions, specified performance and design criteria,
materials, and similar data to show Engineer the services, materials,
and equipment Contractor proposes to provide.
C. Submittals which do not have a fully completed transmittal form
will be returned along with unreviewed attachments. Returned
submittals, even though incomplete, will be counted as a submittal.
d. Before submitting each Shop Drawing or Sample, Contractor shall
have:
1) reviewed and coordinated each Shop Drawing or Sample
with other Shop Drawings and Samples and with the
requirements of the Work and the Contract Documents;