Project Number: 228730
Issue Date: August 2017
WWTE SCADA Upgrades
Nashua, NH
e Requirements for start-up
e Inspection and acceptance of equipment put into service during
construction period
e Access, laydown and coordination with others
Engineer will record minutes and distribute draft copies prior to the
next scheduled meeting to Owner and Contractor for review, then
revise as required and distribute within 2 weeks thereafter to
meeting participants, with copies to Owner and Contractor, and
those affected by decisions made.
Progress Meetings
a.
WOODARD & CURRAN
Owner to schedule progress meetings beginning no later than 60
days after the Initial Conference and continue thereafter on a
monthly basis throughout progress of the Work.
Attendance required by Contractor, Contractor's Superintendent,
major Subcontractors and Suppliers, Owner and Engineer as
appropriate to agenda topics for each meeting.
Agenda:
Review minutes of previous meetings
Unresolved Issues
Review Work progress
Observations, problems, and decisions
Identification of problems which impede planned progress
Review of Schedule of Submittals and status of submittals
Review of off-Site fabrication and delivery schedules
Maintenance of progress schedule
Corrective measures to regain projected schedules
Planned progress during succeeding Work period
Coordination of projected progress
Maintenance of quality and Work standards
Effect of proposed changes on Progress Schedule and
coordination
e Other business relating to Work
Engineer will record minutes and distribute draft copies prior to the
next scheduled meeting to Owner and Contractor for review, then
revise as required and distribute within 2 weeks thereafter to
meeting participants, with copies to Owner and Contractor, and
those affected by decisions made.
OVERALL GENERAL REQUIREMENTS
01 11 05-6