Finance Committee - Agenda - 8/5/2020 - P101

WALDRON ENGINEERING & CONSTRUCTION. INC.
To: William Keating, P.E., Project Engineer, Nashua Wastewater Treatment Facility
From: Jeremy P. Smith, P.E., Waldron Engineering & Construction, Inc.
Date: July 7" , 2020 (revised)
Re: Change Order Request Review 027
NWWTFE Energy Recovery Upgrade Project
Attachments: Methuen Construction PCO-027 Re-coring Stack#2
Mr. Keating:
Waldron has compiled its review based on review of the Owner’s documentation (design
documents, OEM submittals, submittal reviews, RFI responses, and project notes) and the
Contractor’s documentation (RFI’s, Submittals, Reports, issued Change Orders). Specifically;
Waldron has reviewed the issue of additional work associated with the installation of the jacket
water booster pumps. Methuen has previously submitted for the related electrical scope of work.
Summary Review
Original Schedule Schedule Direct Schedule Schedule Claim
Adjustment claim Impact Assessment Recommended
None 1 0 0
Original Cost Cost Adjustment Direct Cost Impact Cost Adjustment
claim Assessment Recommended
None $1,109 $1,109 $1,109
Detailed Review-Base Cost Validity
Methuen has made a claim for the work as required based on RFI responses, submittal reviews
and Field conditions. The claim is based on their work and their subcontractor’s work resulting
from the above. Waldron has reviewed the design documents, OEM submittals, submittal
reviews, and RFI responses regarding this issue. Waldron has relied on vendor quotes, project
cost estimations, historical project data, RS Mcans, and its own proprietary cost data to review the
cost validity of the work scope.
The submitted PCO is based on additions to the work for re-coring of the existing stack
penetration, which was found in the field to be not plumb. Waldron’s opinion is that the out-of-
plumb core was an unforeseen existing condition which the G.C. could not reasonably have
predicted during the project bid.
37 INDUSTRIALDRIVE §SUITEG-1 EXETER,NHO3833 (603) 772-7153 WALDRGN COM
SEED tate peal te Naira
Mr. William Keating
COR review
626/26
Detailed review of the fair market value
Claimed Cost | Fair Market Value | Allowable Mark-up** | Work Value Assessment
of Wark of Work scope
$1,109 $640 (includes 15% on MC Work $1,109
materials & 10% on Subs (<$50k)
equipment}* /-£/2% on Subs (#50-
100Ic)
5% on Subs (>100k)
*Market Value Assessment-$1,082 to $1,624 (1/- 20%)
Detailed Review-Schedule
Methuen made a claim for schedule adjustment but has not provided a CPM (critical path
method) schedule showing how this item moved onfo the critical path, Their schedule claim is
‘ therefore evaluated at 0 days. Therefore we recommend 0 days be awarded.
Original Schedule Schedule Direct Schedule Schedule Claim
Adjustment claim Impact Assessment Recommended
None 1 0 0
Conclusion
Waldron has reviewed all the available information, and has taken into consideration the factors
surrounding the issues in question.
Waldron recommends approving $1,109 of the claim as noted above @ days of schedule relief.
If you have any questions on the above, please don’t hesitate to contact me at 603-772-7153 x
105 or jsmith@waldron.com
Sincerely
Waldron Engineering & Construction, Inc,
Jerony P. Sith, PE,
Jeremy Smith, P-E,
Methuen Construction Co., Inc.
144 Main Street - PO Box 980
Plaistow, New Hampshire 03865
PCO #027
Project; 181012 - Nashua Energy Recovery Upgrade
2 Sawenill Re.
Nashua, New Hampshire 03060
Phone: (603) 328-2222
Prime Contract Potential Change Order #027: Recoring for Chimney Stack
#2
City of Nashua
TO: FROM: Methuen Construction Co., Inc.
229 Main Street 144 Main Sireet PO Box 980
Nashua New Hampshire, 03060 Plaistow New Hampshire, 03865
PCO NUMBER/REVISION: 027/70 CONTRACT: iFBOSO1-G90618 NASHUA PO #146864 -
Nashua Energy Recovery Upgrade
REQUEST RECEIVED FROM: Don Hutchinson (Methuen Construction CREATED BY: Anthony Crespo (Methuen Construction Co.,
Co., Inc,} Ins.)
STATUS: Pending - In Review CREATED DATE: — 6/10 /2020
REFERENCE: — DATE SENT:
FIELD CHANGE: No PRIMECONTRACT None —~—~CS
CHANGE ORDER:
LOCATION: Energy Recovering Building
SCHEDULE IMPACT: 1 day ACCOUNTING Amount Based ,
METHOD:
PAID INFULL: No TOTALAMOUNT: — $1,109.22
Methuen Construction (MC}, hereby submits this PCO in accordance with the documentation referenced herein. It is expressly understood and agreed
that this proposal is valld for the time as specified within this document from the date of tha PCO. The Proposal is based upon current day construction
costs and does not include escalation costs for any material items that are either volatile or market sensilive. This Proposal does not include overlime
acceleration or expediting costs. This proposal does not include the costs associated wilh out of sequence construction, interference, impact related
delays and disruptions. MC reserves its rights under the agreement to seek additional time, indirect and impact costs associated with the PCO, once the
impacts can be fully evaluated. This proposal is submitted based on the understanding that it is exempt from WBE/MBE participation requirements and
acceptance of this proposal waives the participation requirements associated with this additional work.
POTENTIAL CHANGE ORDER TITLE: Recoring for Chimney Stack #2
CHANGE REASON: Existing Condition
POTENTIAL CHANGE ORDER DESCRIPTION; (The Coniract Is Changed As Foflaws)
CE #056 - PCO 27- Recoring Chimney Stack #2
Scope: There were issues running generator #2 exhaust stack through the ceiling. The existing core holes through the roof were nat plumb making it
impossible to run the stack through. MC had to recore the holes se that the stack could properly be erected. The below is a breakdown of the work
performed including, renting core drill, coring through roof, cleanup, etc. As a result MC is requesting 1 day to be added to the overall constructian
schedule.
ATTACHMENTS:
Burden Rate
Subtot:
{43.00% Appiies to Labor} ubtotal
# | Cost Code Dascripiion Typa Amount
22-0300 -
BREECHIN
1 | Ssysten |b
PHPING
Labor $977.36 5 248.26 $825.62
22-0300 -
BREECHIN
2 losysren |EtRment
PIPING
Equipment 5 120.00 30.00 $120.00
Methuen Construction Co., Inc. page 1 of 2 Printed On: 6/10/ 2020 02:42 PM
PCO #027
Subtetal: S697.36 $248.26 $945.62
GC Wark Total Foe» Labor: 15.00% Applies to Labor 5 123.84
GG Wark Total Fee - Material & Equipment: 15.00% Applies to Otter, Matorial, and Equipment. 518.00
G¢ Subcontractors Work Fee: 10,00% Applies to Subcontractor, $0.06
Bond & Ganoral Liability: 2.00% Apalices to Other, Material, Committed Costs, Labor, Rental Equipmont Refef, Equipment, Subcontractor, and Burder. $21.76
Grund Talal: $1,100.22
Jeremy Smith, P.E. (Waldron Engineering
& Construction, Inc.)
37 Industrial Drive Suite G-1
Exeter, New Hampshire 03833
City of Nashua
229 Main Street
Nashua, New Hampshire 03060
Methuen Construction Go., Inc,
144 Main Street PO Box 980
Plaistow, New Hampshire 03865
SIGNATURE DATE
Methuen Construction Co., Inc.
SIGNATURE DATE
page 2 of 2
SIGNATURE DATE
Printed On: 6/10/2020 02 :42 PM
ar industrial Doc #: PCO 27
II sens nruenetn Ref. Document:
PROJECT NAME; Date: a-Jun-20
Nashua Energy Recovery
PROJECT NO: 1813012
PHASE
COST SUMMARY SHEET
Recoring Chimney Stack #2
A MC Labor (Recap Sheet): $825.62
B MC Materials, & Equipment (Recap Sheet): $120.00
c MC Fee (A x 15%) + (B x 15%): $141.84
D Subtotal MC Work (A+B+C)}: | $ 1,087.47
E Total Subcontractors (Below):
F Mc Mark-up on Subcontractor Work (5%, 7.5% or 10%):
G Bond (1%) and General Liability (1%): $21.75
H Original FBS Location Credit $0.00
Total Proposal (D +E +F+G): $ 1,109.22
SUBCONTRACTOR SUMMARY
Subcontractor Description
5
$
$
$
$
3
Total Subcontractors:
Amount
City of Nashua
Purchasing Department
Administrative Services Division (603) 589-3330
229 Main Street - Nashua, NH 03060 Fax (603) 594-3233
June 29, 2022
Memo #23-300
TO: Mayor Donchess
Finance Committee
SUBJECT: Copier Leases & Maintenance in the amount not to exceed $29,250 funded from 54421
Copier Maintenance/General Fund
Please see attached communications from Dan McMullen, IT Manager of Technical Services, dated June
14, 2022 for project specific details related to this purchase. Below please find a summary of the purchase
approval request:
Item: Replacement/renewal for 4 coper leases for Wastewater, Human Resources,
Assessing & Legal
Value: $487.50 per month for a 60 month term to total $29,250
Vendor: Conway Office/Xerox Financial
Department: 122 Information Technology
Source Fund: 54421 Copier Maintenance/ General Fund
Ordinance: Pursuant to § 5-84 Special purchase procedures. A/({7) Purchases under extensions
of contracts when no price increase exceeds 10% per year.
The Administrative Services Division: Information Technology, and the Purchasing Department
respectfully request your approval of this contract.
Regards,
Kelly Parkinson
Purchasing Manager
Ce: K Kleiner
J Graziano
Recoring Chimney Stack #2
Scope: There were issues aunning generalor #2 exhaust slack through the ceiling. The existing core holes through ihe reof were not plumb making il impossible lo run the
aiack thraugh. MC had to recore the holes sa that the stack could properly be erected. The below is a breakdown of the work performed including, renting core drill, cering
through roof, cleanup, atc, As a result MC Js requesting 4 day fo be added Io the overall construction schedule,
1-LABOR
CATEGORY HRS RATEHHR PREMIUM SUBTOTAL = LINE TOTAL TOTAL
DRIVER
AL $577.35
2-MATERIALS
DESCRIPTION ary UNIT UNITCOST SUBTOTAL
SUBTOTAL 5 -
3-EQUIPMENT Eo
CATEGORY QTY RATE UNIT SUBTOTAL
VATOR PC300 5190
FRONT END LOADER
SUBTOTAL $120.00
Page 2015 6/10/2020 - 2:33 PM
WALDRON ENGINEERING & CONSTRUCTION. INC.
To: William Keating, P.E., Project Engineer, Nashua Wastewater Treatment Facility
Piom: Jeremy P. Sinith, FE., Waldron Engineering & Construction, inc.
Date: March 28, 2020
Re: Change Order Request Review 028
NWWTE Energy Recovery Upgrade Project
Attachments: Methuen Construction PCO-028 Electrical items (list of six)
Mr. Keating:
Waldron has compiled its review based on review of the Owner’s documentation (design
documents, OEM submittals, submittal reviews, RFI responses, and project notes) and the
Contractor’s documentation (RFI’s, Submittals, Reports, issued Change Orders). Specifically;
Waldron has reviewed the issue of additional work associated with the installation of the jacket
water booster purops. Methuen has previously submitted for the related electrical scope of work.
Summary Review
Original Schedule Schedule Direct Schedule Schedule Claim
Adjustment claim Impact Assessment Recommended
None 14 0 0
Original Cost Cost Adjustment Direct Cost Impact Cost Adjustment
claim Assessment Recommended
None $17,168 $736 3736
Detailed Review-Base Cost Validity
Methuen has made a claim for the work as required based on RFI responses, submittal reviews
and Field conditions. The claim is based on their work and their subcontractor’s work resulting
from the above. Waldron has reviewed the design documents, OEM submittals, submittal
reviews, and RFI respouses regarding this issue. Waldron has relied on vendor quotes, project
cost estimations, histozical project data, RS Means, and its own proprietary cost data to review the
cost validity of the work scope,
The submitted PCO is based on additions to the work for various electrical items which MC
believes are additional to the project, The various items are summarized in the next sheet as to
their validity and any specific reasons. Generally, items which are unforesecable-unknow existing
conditions or legitimate additional work requested by others are recommended, Those that are
foreseeable work due to conditions that could have or should have been assessed during bid
walkthroughs, or are the result of trade-to-itade coordination (which is the responsibility of the
G.C.} are not recommended.
37 INDUSTRIALDAIVE SUTEG-1 EXETER,NHDSB83 (603}772-7153 WaALOON GM
Bub A Tt ho pena ay s Fhe 2e3!
a sasrrseenenreniam eSeens cep ees efincasic! Sr ureter = repeats arm
Mr. William Keating
COR review
6126/20
1-Oas Deleclor
Datnaged by coring | Nu (Foreseeable/Trade cour.) | $5,191
Wiring worl
2-Plant Phone Wiring | Damaged by sawing | No (Foresceable/Trade coor.) | $2,911
work
3-New Boiler Room | Added work Yes (Legitimate Add) $736
Cir. Pumps
4-Thermostat Wiring | Damaged by sawing No (Foreseeable/Trade coor.) | $1,038
work
5-Receptacle Wiring | Damaged by sawing | No (Foreseeable/Txade coor.) | $2,696
work
6-Ext. Light Wiring | Damaged by Wall No (Foreseeable/Trade coor.) | $4,583
demo
Therefore, of the list of Work items #1-6 above, only #3 appears to be an extra item
As such, work item #3 will be evaluated for total market value
Only Work Stem #3 (take the higher assessed value or the claim, whichever is lower)
Claimed Cost | Fair Market Value | Allowable Mark-up** | Work Value Assessment
of Work of Work scope
$736 $684 (includes 18% on MC Work $736
materials && 10% on Subs (<$50k)
equipment)* 7-1/2% on Subs ($50-
100k)
5% on Subs (+100k}
*Market Value Assessment-3602 to $903 (4/- 20%)
Detailed Review-Schedule
Methuen made a claim for schedule adjustment but has not provided a CPM (critical path
method) schedule showing how this item moved onto the critical path. Their schedule claim is
therefore evaluated at 0 days. Therefore we recommend 0 days be awarded,
Original Schedule Sehedule Direct Schedule Schedule Claim
Adjustment claim Impact Assessment Recommended
None 14 0 0