Mr. William Keating
COR review
626/26
Detailed review of the fair market value
Claimed Cost | Fair Market Value | Allowable Mark-up** | Work Value Assessment
of Wark of Work scope
$1,109 $640 (includes 15% on MC Work $1,109
materials & 10% on Subs (<$50k)
equipment}* /-£/2% on Subs (#50-
100Ic)
5% on Subs (>100k)
*Market Value Assessment-$1,082 to $1,624 (1/- 20%)
Detailed Review-Schedule
Methuen made a claim for schedule adjustment but has not provided a CPM (critical path
method) schedule showing how this item moved onfo the critical path, Their schedule claim is
‘ therefore evaluated at 0 days. Therefore we recommend 0 days be awarded.
Original Schedule Schedule Direct Schedule Schedule Claim
Adjustment claim Impact Assessment Recommended
None 1 0 0
Conclusion
Waldron has reviewed all the available information, and has taken into consideration the factors
surrounding the issues in question.
Waldron recommends approving $1,109 of the claim as noted above @ days of schedule relief.
If you have any questions on the above, please don’t hesitate to contact me at 603-772-7153 x
105 or jsmith@waldron.com
Sincerely
Waldron Engineering & Construction, Inc,
Jerony P. Sith, PE,
Jeremy Smith, P-E,