Finance Committee - Agenda - 8/5/2020 - P113

By dnadmin on Mon, 11/07/2022 - 13:27
Document Date
Fri, 07/31/2020 - 13:23
Meeting Description
Finance Committee
Document Type
Agenda
Meeting Date
Wed, 08/05/2020 - 00:00
Page Number
113
Image URL
https://nashuameetingsstorage.blob.core.windows.net/nm-docs-pages/fin_a__080520…

PCO #028

Subtotal} $15,476.14 $0.00 315,476.14
GC Work Total Fee - Labor; 15.00% Applies to Labor. $0.00
GC Work Tofal Fee - Material & Equipment: 15.00% Applies to Other, Material, and Equipment. $0.00
GC Subcontractors Work Fee: = 8.7% Applies to Subcontractor. $1,345.75
Bond & Ganeral Lfabillty: 2.00% Appliles to Other, Material, Committed Casts, Labor, Rantal Equipment Relief, Equipment, Subcontractor, and Burden. S$ 336,44
Grend Total: $17,168.33
Jeremy Smith, P.E. (Waldron Engineering City of Nashua Methuen Construction Co., Inc.
& Construction, Inc.}
37 Industrial Drive Suite G-1 229 Main Street 144 Main Street PO Box 980
Exeter, New Hampshire 03833 Nashua, New Hampshire 03060 Plaistow, New Hampshire 03865
SIGNATURE DATE SIGNATURE DATE SIGNATURE DATE

Methuen Construction Co., Inc.

page 2 of 2

Printed On: 6/10/ 2020 02:51 PM

Page Image
Finance Committee - Agenda - 8/5/2020 - P113

Finance Committee - Agenda - 8/5/2020 - P114

By dnadmin on Mon, 11/07/2022 - 13:27
Document Date
Fri, 07/31/2020 - 13:23
Meeting Description
Finance Committee
Document Type
Agenda
Meeting Date
Wed, 08/05/2020 - 00:00
Page Number
114
Image URL
https://nashuameetingsstorage.blob.core.windows.net/nm-docs-pages/fin_a__080520…

Mipeindustral Doc #: PCO 28

I ne mee rein Ref. Document:

PROJECT NAME: Date: 2-Jun-20

Nashua Energy Recovery
PROJECTNO: 181012
PHASE
COST SUMMARY SHEET
Basic Electrical- Conduit Relocations
A McC Labor (Recap Sheet): $0.00
B Mc Materials, & Equipment (Recap Sheet); $0.00
c McG Fee (A x 15%} + (B x 15%): $0.00
D Subtotal MC Work (A+B#C): | $ -
E Total Subcontractors (Below): $15,476.14
F McC Mark-up on Subcontractor Work (5%, 7.5% or 16%): | $ 1,345.75
G Bond (1%) and General Liability (1%): $336.44
H Original FBS Location Credit $0.00
Total Proposal (D+E+F+G)}: $ 17,158.33

SUBCONTRACTOR SUMMARY

Subcontractor Description

Eil Conduit Relocations CO 12-47

Total Subcontractors:

Amount

$ 15,476.74

3
$
$
$
$
$

45,476.14

Page Image
Finance Committee - Agenda - 8/5/2020 - P114

Finance Committee - Agenda - 8/5/2020 - P115

By dnadmin on Mon, 11/07/2022 - 13:27
Document Date
Fri, 07/31/2020 - 13:23
Meeting Description
Finance Committee
Document Type
Agenda
Meeting Date
Wed, 08/05/2020 - 00:00
Page Number
115
Image URL
https://nashuameetingsstorage.blob.core.windows.net/nm-docs-pages/fin_a__080520…
Page Image
Finance Committee - Agenda - 8/5/2020 - P115

Finance Committee - Agenda - 8/5/2020 - P116

By dnadmin on Mon, 11/07/2022 - 13:27
Document Date
Fri, 07/31/2020 - 13:23
Meeting Description
Finance Committee
Document Type
Agenda
Meeting Date
Wed, 08/05/2020 - 00:00
Page Number
116
Image URL
https://nashuameetingsstorage.blob.core.windows.net/nm-docs-pages/fin_a__080520…

WALDRON EMSINEERING & CONSTRUCTION, INC.

To: William Keating, P.E., Project Engineer, Nashua Wastewater Treatment Facility
From: Jeremy P. Smith, P.E., Waldron Engineering & Construction, Inc.
Date: July 9" , 2020
Re: Change Order Request Review 029
NWWTF Energy Recovery Upgrade Project
Attachments: Methuen Construction PCO-029 HMI programming
Mr. Keating:

Waldron has compiled its review based on review of the Owner's documentation (design
documents, OEM submittals, submittal reviews, RFI responses, and project notes) and the
Contractor’s dacumentation (RFI’s, Submittals, Reports, issued Change Orders). Specifically;
Waldron has reviewed the issue of additional work associated with the installation of the jacket
water booster pumps. Methuen has previously submitted for the related electrical scope of work,

Summary Review

Original Schedule Schedule Direct Schedule Schedule Claim
Adjustment claim impact Assessment Recommended
None 2 0 0
Original Cast Cost Adjustment Direct Cost Impact Cost Adjustment
elaim Assessment Recommended
None $13,452.26 $10,454 $10,454

Detailed Review-Base Cost Validity

Methuen has made a claim for the work as required based on RFI responses, submittal reviews
and Field conditions. The claim is based on their work and their subcontractor’s work resulting
from the above. Waldron has reviewed the design documents, OEM submittals, submittal
reviews, and RFI responses regarding this issue. Waldron has relied on vendor quotes, project
cost estimations, historical project data, RS Means, and its own proprietary cost data to review the
cost validity of the work scope.

The submitted PCO is based on additions to the work encountered in the field around Engineering
change notice (ECN) regarding transfer of the HMI programming scope from NWWTF as a self-
perform, to add to the contractors’ scope of work. As this is added work, the addition is valid, and
needs only the assessment of the FMV.

WALORON COM

37 INOUSTRIAL DRIVE §=SUIFEG-1 EXGTER,NH 09833 (603)772-7153

Page Image
Finance Committee - Agenda - 8/5/2020 - P116

Finance Committee - Agenda - 8/5/2020 - P117

By dnadmin on Mon, 11/07/2022 - 13:27
Document Date
Fri, 07/31/2020 - 13:23
Meeting Description
Finance Committee
Document Type
Agenda
Meeting Date
Wed, 08/05/2020 - 00:00
Page Number
117
Image URL
https://nashuameetingsstorage.blob.core.windows.net/nm-docs-pages/fin_a__080520…

Mr. William Keating
COR review
7/920

' The table below summarizes the total value of the work, which will be assessed value of the work
performed at fair market conditions with no deducts or mark-down %.

The claimed cost of work (take the lower of the higher estimate or the claim)

Claimed Cost | Fair Market Value | Allowable Mark-up** | Work Value Assessment
of Work of Work scepe
$13,452.26 $7,920 (includes 15% on MC Work $10,454
materials & 10% on Subs (<$50k)
equipment)* 7-1/2% on Subs ($50-
100k}
5% on Subs (> 100k)
*Market Value Assessment-$6,970 to $10,454 (+/- 20%)
Work Value | Deduct Assessment i Mark down by 0% as Total Direct Value
Assessment noted above Assessment
510,454 (30) $0 $10,454

Detailed Review-Schedule

Methuen made a claim for schedule adjustment but has not provided a CPM (critical path
method) schedule showing how this item moved onto the critical path. Their schedule claim is
therefore evaluated at 0 days. Therefore we recommend 0 days be awarded.

Original Schedule Schedule Direct Schedule Schedule Claim
Adjustment claim Impact Assessment Recommended
None 2 0 0
Conclusion

Waldron has reviewed all the available information, and has taken into consideration the factors
surrounding the issues in question.

Waldron recommends approving $10,454 of the claim as noted above Q days of schedule relief.

If you have any questions on the above, please don’t hesitate to contact me at 603-772-7153 x
105 or jsmith@waldron.com

Sincerely
Waldron Engineering & Construction, Inc.

” Jercmy P. Saith, PE.
Jeremy Smith, P.£.

Page Image
Finance Committee - Agenda - 8/5/2020 - P117

Finance Committee - Agenda - 8/5/2020 - P118

By dnadmin on Mon, 11/07/2022 - 13:27
Document Date
Fri, 07/31/2020 - 13:23
Meeting Description
Finance Committee
Document Type
Agenda
Meeting Date
Wed, 08/05/2020 - 00:00
Page Number
118
Image URL
https://nashuameetingsstorage.blob.core.windows.net/nm-docs-pages/fin_a__080520…

ot

iMethuer PCO #029
SONSTRUCTION
ee

Methuen Construction Co., Inc. Project: 787012 ~ Nashua Energy Recovery Upgrade
144 Main Street - PO Box 980 2 Sawmill Rd.
Piaislow, New Hampshire 03865 Nashua, New Hampshire 03060

Phone: (603) 328-2222

Prime Contract Potential Change Order #029: PCO 029- SCADA HMI

Interface
TO: City of Nashua FROM: Methuen Construction Co., Inc.
229 Main Street 144 Main Street PO Box 980
Nashua New Hampshire, 92060 Plaistow New Hampshire, 03865
PCO NUMBER/REVISION: 029 /0 CONTRACT: IFB0501-090618 NASHUA PO #146861 -

Construction, inc.) Inc.)

STATUS: Pending - In Review ' GREATED DATE: 7/9/2020

a

FIELD CHANGE: —~—~—~—~&No PRIME CONTRACT None
CHANGE ORDER:

LOCATION:

SCHEDULE IMPACT: 2days ACCOUNTING Amount Based ”
METHOD:

-PAIDIN FULL: “No TOTAL AMOUNT: $13,452.26 ° ~ _—

Methuen Construction (MC), hereby submits this PCO in accordance with the documentation referenced herein, It is expressly understood and agreed
that this proposal Is valid for the time as specified wilhin this document from the date of the PCO, The Proposal is based upon current day construction
costs and does not include escalation costs for any material itams that ara either volatile or market sensitive, This Proposal) does not include overtime
acceleration or expediiing costs. This proposa! does not include the costs associated with out of sequence construction, interference, impact related
delays and disruptions. MC reserves its rights under the agreement to seek additional time, indirect and impact costs associated with ihe PCO, once the
impacts can be fully evaluated. This proposal is submitted based on the understanding that it is exempt from WBE/MBE participation requirements and
acceptance of this proposal waives the participation requirements associated with this additional work.

POTENTIAL CHANGE ORDER TITLE: PCO 029- SCADA HME Interface
CHANGE REASON: Design Development

POTENTIAL CHANGE ORDER DESCRIPTION: (The Contract is Changed As Follows)

CE #062 - PCO 29- SCADA HMI Interface

Per Waldrens ECN-005, Ell will install SCADA HMI interface screens for WWTF Energy recovery equipment to match those provided in 409423 2.04.4.
Eit will also develop SCADA screens and test with PLC45. Transfer to all SCADA nodes, and train operators as needed. MC requests 2 additional days
fo be added to the overall construction schedule. We have included 2 days of on-site supervision to cover this additional work,

ATTACHMENTS:
ECN-005 SCADA Sereen Development.doc.ndt

Burdon Rate :
@ | Gost Code Deseription Type Arriount {43.00% Appling to Lebar) Subtotal

26-0100 -
BASIC Subcontract
1 ELECTRICA SUBCONTRACTOR or 3 10,193.25 3 6,00 $10,403.25

L

01-0530 -
2 | SUPERINTE | LABOR Labor 34,154.72 $496.53 $1,651.25
NDENT

Methuen Construction Ca., Inc. page 1 of 2 Printed On: 7/9/2020 10:27 AM

Page Image
Finance Committee - Agenda - 8/5/2020 - P118

Finance Committee - Agenda - 8/5/2020 - P119

By dnadmin on Mon, 11/07/2022 - 13:27
Document Date
Fri, 07/31/2020 - 13:23
Meeting Description
Finance Committee
Document Type
Agenda
Meeting Date
Wed, 08/05/2020 - 00:00
Page Number
119
Image URL
https://nashuameetingsstorage.blob.core.windows.net/nm-docs-pages/fin_a__080520…

PCO #029

04-0530 ~
3 | SUPERINTE | EQUIPMENT Equipment 3 192,00 $0.00 $192.00
NOENT
$496,53 $12,026.50

Subtotak| $11,525.97 |

GG Work Total Fee ~ Labor: 15.00% Applies to Labor, $ 247.69
GC Work Total Foe « Material & Equipment: 15.00% Applies to Other, Material, and Equipment. $28.80
Gt Subcontractors Work Fas: 3 6,/% Applias to Subcontractor, S665.U
Bond & General Liability: 2,00% Appling to Ciker, Matorlal, Committed Costs, Labor, Rentat Equipment Reflof, Equipment, Subcantractey, and Burden. $263.77
Grand Total: $13,452.26
Jeremy Smith, PE. (Waldron Engineering City of Nashua Methuen Construction Co., Inc.
& Gonstruction, Inc.)
37 Industrial Drive Suite G-4 229 Main Street 144 Main Streat PO Box 980
Exeter, New Hampshire 03833 Nashua, New Hampshire 03060 Plaistow, New Hampshire 03865
SIGNATURE DATE SIGNATURE DATE SIGNATURE DATE

Methuen Construction Co., Inc.

page 2 of 2

Printed On: 7/9/2020 10:21 AM

ay

Page Image
Finance Committee - Agenda - 8/5/2020 - P119

Finance Committee - Agenda - 8/5/2020 - P120

By dnadmin on Mon, 11/07/2022 - 13:27
Document Date
Fri, 07/31/2020 - 13:23
Meeting Description
Finance Committee
Document Type
Agenda
Meeting Date
Wed, 08/05/2020 - 00:00
Page Number
120
Image URL
https://nashuameetingsstorage.blob.core.windows.net/nm-docs-pages/fin_a__080520…

ae

[AE Industreal Doc #: PCO 29
Seg ES Ref. Document:
PROJECT NAME: Date: 8-Jul-20
Nashua Energy Recovery
PROJECT NO: 181012
PHASE
COST SUMMARY SHEET
SCADA HMI Interface
A McC Labor (Recap Sheet): $1,651.25
B MC Materials, & Equipment (Recap Sheet): $192.00
Cc McC Fee (A x 15%) + (B x 15%): $276.49
D Subtotal MC Work (A+B+C}; | $ 2,119.74
E Total Subcontractors (Below): $10,183.25
F McC Mark-up on Subcontractor Work (5%, 7.5% or 10%}: | $ 885.50
G Bond (1%) and General Liability (4%): $263.77
H Original FBS Location Credit $0.00
Total Proposal (D+E+F+G); $ 13,452.26
SUBCONTRACTOR SUMMARY
Subcontractor Description Amount
- SCADA HMI Interface per attached quote &
Ell ECN-005 $ 10,183.25
g -
4 -
a -
g -
5 -
Total Subcontractors: $ 10,183.25

Page Image
Finance Committee - Agenda - 8/5/2020 - P120

Finance Committee - Agenda - 8/5/2020 - P121

By dnadmin on Mon, 11/07/2022 - 13:27
Document Date
Fri, 07/31/2020 - 13:23
Meeting Description
Finance Committee
Document Type
Agenda
Meeting Date
Wed, 08/05/2020 - 00:00
Page Number
121
Image URL
https://nashuameetingsstorage.blob.core.windows.net/nm-docs-pages/fin_a__080520…

ts

Page Image
Finance Committee - Agenda - 8/5/2020 - P121

Finance Committee - Agenda - 8/5/2020 - P122

By dnadmin on Mon, 11/07/2022 - 13:27
Document Date
Fri, 07/31/2020 - 13:23
Meeting Description
Finance Committee
Document Type
Agenda
Meeting Date
Wed, 08/05/2020 - 00:00
Page Number
122
Image URL
https://nashuameetingsstorage.blob.core.windows.net/nm-docs-pages/fin_a__080520…

WALDRON ENGINEERING & CONSTRUCTION, INC.

To: William Keating, P.E., Project Engineer, Nashua Wastewater Treatment Facility
From: Jeremy P. Smith, P.E., Waldron Engineering & Construction, Inc.

Date: July 9" , 2020

Re: Change Order Request Review 030

NWW'EF Energy Recovery Upgrade Project

Attachments: Methven Construction PCO-030 Gas Level transmitter

Mr. Keating:

Waldron has compiled its review based on review of the Owner’s documentation (design
documents, ORM submittals, submittal reviews, RFI responses, and project notes) and the
Contractor’s documentation (RFI’s, Submittals, Reports, issued Change Orders). Specifically;
Waldron has reviewed the issue of additional work associated with the installation of the jacket
water booster pumps. Methuen has previously submitted for the related electrical scope of work.

Summary Review

Original Schedule Schedule Direct Schedule Schedule Claim
Adjustment claim Impact Assessment Recommended
None 2 0 0
Original Cost Cost Adjustment Direct Cost Impact Cost Adjustment
claim Assessment Recommended
None 97,707.75 $7,623 57,623

Detailed Review-Base Cost Validity

Methuen has made a claim for the work as required based on RFI responses, submittal reviews
and Field conditions. The claim is based on their work and their subcontractor’s work resulting
from the above. Waldron has reviewed the design documents, OEM submittals, submittal
reviews, and RFI responses regarding this issue. Waldron has relied on vendor quotes, project
cost estimations, historical project data, RS Means, and its own proprietary cost data to review the
cost validity of the work scope.

The submitted PCO is based on additions to the work encountered in the field around additions of
the gas level transmitters to the PLC-15 systern. Previously these transmitters were not connected,
and this is additional work to the project. A FMV will be performed.

&? INDUSTRIALDORIVVE SUNEG-1 EXETER,NHOG833 (603}772-7153 WALDRON COM

Page Image
Finance Committee - Agenda - 8/5/2020 - P122

Pagination

  • First page « First
  • Previous page ‹‹
  • …
  • Page 3506
  • Page 3507
  • Page 3508
  • Page 3509
  • Current page 3510
  • Page 3511
  • Page 3512
  • Page 3513
  • Page 3514
  • …
  • Next page ››
  • Last page Last »

Search

Meeting Date
Document Date

Footer menu

  • Contact