Board Of Aldermen - Minutes - 3/21/2022 - P24
Stairwell ADA Modifications
Stairwell ADA Modifications
Restroom Upgrades
14
Current Dumpster Location
15
16
Site Traffic & Safety Considerations
Franklin St (Left) & Charles St (Right)
17
Site Traffic & Safety Considerations
Winter St (Left, Center), Locust St (Right)
Miscellaneous Other Work
Main Entrance Rear Entrance Old Water Fountains
Basement Basement Basement Fire Extinguishers io
Key Construction Elements
Summer 2023
¢ Replacement of Asbestos containing flooring and old carpeting.
¢ Replacement of 3" floor Asbestos containing sheetrock walls.
¢ Replacement of roof membrane.
¢ After the roof is replaced, we plan to have solar panels installed on
the roof to offset the cost of electricity.
Reflooring & New Walls (3'¢ Floor)
21
Contingencies
¢ Part of the proposed bond includes contingencies for two areas:
1. Owner/Architect Contingency — This is to cover unseen or
unknown conditions uncovered during the course of construction, and
the addition of scope items requested by the JSSBC. 10% of the
construction budget was set aside for this.
2. Site Upgrades Identified By Traffic Consultant — After the
consultant conducts their observations of current conditions and
makes recommendations for improvements, the JSSBC will decide on
which (if any) of the improvements to implement. 5% of the
construction budget was set aside for this.
22