The Turner Group shall attend project progress and review meetings and
provide discussion and documentation of contract work performed, work in
progress, problems and obstacles encountered, solutions proposed, anda
proposed work schedule. Project progress and review meetings shall be
scheduled at an appropriate time and will include meeting minutes/notes to
memorialize the discussions. During construction The Turner Group shall attend
weekly progress meetings.

Finance Committee - Agenda - 1/15/2020 - P36

By dnadmin on Mon, 11/07/2022 - 13:33
  • Read more about Finance Committee - Agenda - 1/15/2020 - P36

regulatory agencies, the equipment supplier, the Contractor, the
interconnecting utility, and all other required stakeholders.

10

Finance Committee - Agenda - 1/15/2020 - P35

By dnadmin on Mon, 11/07/2022 - 13:33
  • Read more about Finance Committee - Agenda - 1/15/2020 - P35

® Proposed Plan, Section & Details
® Proposed Powerhouse HVAC Plan, Section & Details

The Turner Group shall prepare a preliminary draft of the following project
documents: final project report, construction specifications, and other
miscellaneous project documents, including, project design criteria, project
development schedule, and regulatory applications. We shall submit all final
reports, manuals and regulatory applications for final review and approval.

Finance Committee - Agenda - 1/15/2020 - P34

By dnadmin on Mon, 11/07/2022 - 13:33
  • Read more about Finance Committee - Agenda - 1/15/2020 - P34

The Turner Group shall prepare specific drawings necessary for construction of
the new powerhouse and installation of the new turbine/generator and ancillary
equipment.

Drawings for this project will include (as needed), and may be limited to the following:

e Existing Conditions Site Plan(s)

e Existing Conditions Intake Plan

e Existing Conditions Section(s)

e Existing Conditions Powerhouse Floor Plan

e Existing Conditions Roof Plan

e Mavel General Arrangement Plan
e Mavel Waterway Passage Plan

e Mavel TGC Plan(s}

Finance Committee - Agenda - 1/15/2020 - P33

By dnadmin on Mon, 11/07/2022 - 13:33
  • Read more about Finance Committee - Agenda - 1/15/2020 - P33

10.

Finance Committee - Agenda - 1/15/2020 - P32

By dnadmin on Mon, 11/07/2022 - 13:33
  • Read more about Finance Committee - Agenda - 1/15/2020 - P32

assessment and review of: foundation subgrade, material and conditions;
subgrade material placement, compaction and testing; concrete placement
and testing; material and equipment samples, submittals and test data. On
behalf of the City, The Turner Group will subcontract with testing companies
who will provide quality assurance and quality control on materials being
installed for, but not limited to, concrete reinforcement, concrete mixes, and
mechanical air flow ventilation for the powerhouse. Electrical testing will be

Finance Committee - Agenda - 1/15/2020 - P31

By dnadmin on Mon, 11/07/2022 - 13:33
  • Read more about Finance Committee - Agenda - 1/15/2020 - P31

turbines, generators, control gates, switchgear, control panels, all other auxiliary
mechanical and electrical equipment, and other space provisions.

We shall prepare documentation for start-up and testing procedures and
requirements.

C. Regulatory Applications

Finance Committee - Agenda - 1/15/2020 - P30

By dnadmin on Mon, 11/07/2022 - 13:33
  • Read more about Finance Committee - Agenda - 1/15/2020 - P30

Soil/rock borings may be required as part of this investigation, if deemed
necessary by the design team.

Plant Design and Construction Documents

We shall perform professional services as hereinafter stated including
customary, civil, structural, hydraulic, mechanical, and electrical services and
customary architectural services in connection with the preparation of
construction documents for the installation of the TGC.

Finance Committee - Agenda - 1/15/2020 - P29

By dnadmin on Mon, 11/07/2022 - 13:33
  • Read more about Finance Committee - Agenda - 1/15/2020 - P29

drawings and other information forwarded by or to the City pertaining to the
project.

Turbine/Generator/Controls (TGC) Coordination

The Turner Group will review and provide comments to the City regarding the
final TGC purchase contract.

Finance Committee - Agenda - 1/15/2020 - P28

By dnadmin on Mon, 11/07/2022 - 13:33
  • Read more about Finance Committee - Agenda - 1/15/2020 - P28

EXHIBIT B
HL Turner Scope of Services
Jackson Mills Turbine/Generator/Controls Upgrade Project
Nashua, New Hampshire

The Jackson Mills Hydroplant Turbine/Generator/Controls Upgrade Project (”project”) is the
subject of Agreements between the City of Nashua and Bancroft Contracting Corporation
and the City of Nashua and Mavel Americas. Project work is described in that Agreement
along with a general description of the Engineer’s role representing the City of Nashua.