assessment and review of: foundation subgrade, material and conditions;
subgrade material placement, compaction and testing; concrete placement
and testing; material and equipment samples, submittals and test data. On
behalf of the City, The Turner Group will subcontract with testing companies
who will provide quality assurance and quality control on materials being
installed for, but not limited to, concrete reinforcement, concrete mixes, and
mechanical air flow ventilation for the powerhouse. Electrical testing will be
performed by our Electrical Subconsultant, as they and the governing utility
deem necessary to confirm compliance with regulatory requirements. The
Turner Group fee shall include construction testing including: concrete,
geotech, and final “Third Party” electrical testing of protective relays per the
utility approvals for the project.
Be present at the project site to observe and document critical activities,
including: excavation, construction, assembly, installation, monitoring and
testing.
During the manufacture and factory testing of the turbine/generator
equipment, The Turner Group may visit the manufacturing and testing
facilities to visually inspect, monitor, and document the progress schedule,
workmanship, specification compliance, operation and performance testing,
and operating characteristics.
Assist and participate in the initial start-up, testing, and commissioning of
the project, including, but not limited to: training personnel, check-out and
testing of mechanical, electrical instrumentation, and control systems;
turbine performance confirmation, and general preparation of the facility for
operational readiness.
Review the Contractor’s request for progress payments; advise the City as to
the extent of the work completed in accordance with the terms of the
contract documents as of the date of the Contractor's payment request; and
issue for processing by the City certificates for payment in the accepted
amount.
Prepare and submit to the City a Weekly Construction Progress Report.
Project reporting to include: 1). weekly project meeting minutes, 2). field
observation reports with photos, and 3). a monthly report including 1). and
2). plus a schedule and budget report. The report shall summarize all events