10.
associated with the construction of the project during the past week,
including, but not limited to: ongoing discussions with the City of Nashua,
state/federal agencies, and other interested parties; description of and
reason for any construction delays or accelerations, problems encountered,
corrective action (taken or proposed), and change orders under
consideration or approved; proposed and approved changes in project
design, drawings, and specifications; description of construction, material,
and equipment defects and proposed or completed rectification;
documents, samples, and test data submitted and approved or rejected,
issuance of revised or additional drawings and specifications; current
construction progress schedule; and a monthly progress payment request in
accordance with the terms of compensation outlined herein.
Conduct a final review to determine if the project is substantially complete,
provide a written determination that the project has been completed in
general accordance with the contract documents and the Contractor has
substantially completed all of the contract obligations. Upon satisfactory
review, the Turner Group shall prepare a Certificate of Completion and
submit to the City for processing and approval.
11. Transmit to the City all Vendor guarantees, affidavits, releases, bonds, and
12.
waivers to be furnished by the Contractor and the equipment supplier
during the course of project construction.
Upon completion of the construction and successful operation of the
project, The Turner Group shall prepare a final report documenting the as-
built condition of the project. The final project report shall summarize all
change orders issued during the Design and Construction phases of the
project. Change orders generating a change in the scope of the project, or
modifications to the drawings and specifications shall be identified. The final
project report shall document all modifications during the construction,
“as-built” drawings, start-up, testing, or initial operation phase of the project
which resulted in changes in design criteria, design and engineering
analyses, plant performance, plant operating scheme, or the power sales
scheme.
E. Documentation and Presentation
1.
Submittals and Approvals