The Turner Group shall prepare specific drawings necessary for construction of
the new powerhouse and installation of the new turbine/generator and ancillary
equipment.
Drawings for this project will include (as needed), and may be limited to the following:
e Existing Conditions Site Plan(s)
e Existing Conditions Intake Plan
e Existing Conditions Section(s)
e Existing Conditions Powerhouse Floor Plan
e Existing Conditions Roof Plan
e Mavel General Arrangement Plan
e Mavel Waterway Passage Plan
e Mavel TGC Plan(s}
® Mavel Sections
e Mavel Details
e Mavel Mechanical Equipment Plan
e Mavel Electrical Equipment Plan
e Mavel TGC Controls Plan
e Mavel TGC Controls Plan Details
® Proposed Site Plan(s)
e Proposed Powerhouse & Intake Plan
e® Proposed Powerhouse Section
e Proposed Powerhouse Floor Plan
e Proposed Powerhouse Roof Plan
© Proposed Powerhouse Sections
e Proposed Powerhouse Details
e Proposed Powerhouse Electrical Plan(s)
e Proposed Electrical Transformer Building