Board Of Aldermen - Agenda - 4/12/2022 - P203

By dnadmin on Mon, 11/07/2022 - 07:45
  • Read more about Board Of Aldermen - Agenda - 4/12/2022 - P203

Measurement:

The quantity of Flaggers will be measured by the HOUR based on the actual
number of hours authorized, as determined by the Engineer. The Contractor
shall supply qualified flaggers as stated in Section 618 of the NHDOT
Standard Specifications for Road and Bridge Construction, (Approved and
Adopted in 2016). Daily coverage needs to be approved by the Engineer. The
Contractor's schedule for flaggers shall be agreed upon cooperatively with the
Engineer.

Board Of Aldermen - Agenda - 4/12/2022 - P202

By dnadmin on Mon, 11/07/2022 - 07:45
  • Read more about Board Of Aldermen - Agenda - 4/12/2022 - P202

Mobilization shall be measured as a LUMP SUM as specified herein. The total
cost for this item shall not exceed 5 percent of the total of all bid items
excluding this item.

Payment:
The contract price for ITEM 18 shall constitute full compensation to the

Board Of Aldermen - Agenda - 4/12/2022 - P201

By dnadmin on Mon, 11/07/2022 - 07:45
  • Read more about Board Of Aldermen - Agenda - 4/12/2022 - P201

Payment:
The accepted quantity of trees removed shall be paid for at the contract unit

price under the appropriate subdivisions of ITEM 15 (A thru C) and shall
constitute full compensation for removal of the tree, branches, stump and any
undergrowth within the canopy of the tree, and disposal of all wooded material
off-site in a legal manner, all as specified in these Specifications and as
directed by the Engineer.

Note: The Contractor shall file the /nfent to Cut form, and pay the timber tax
under this Item of work.

Board Of Aldermen - Agenda - 4/12/2022 - P200

By dnadmin on Mon, 11/07/2022 - 07:45
  • Read more about Board Of Aldermen - Agenda - 4/12/2022 - P200

NEW VERTICAL GRANITE CURB (STRAIGHT)

Measurement:

The quantity to be measured under ITEM 13B, New Vertical Granite Curb
(STRAIGHT), shall be measured by the LINEAR FOOT in accordance with
the Contract Drawings, directions from the Engineer, and as specified herein.

Payment:
The approved quantity of New Vertical Granite Curb (STRAIGHT) shall be

Board Of Aldermen - Agenda - 4/12/2022 - P199

By dnadmin on Mon, 11/07/2022 - 07:45
  • Read more about Board Of Aldermen - Agenda - 4/12/2022 - P199

excavation and disposal of existing pavement and existing unsuitable materials
at the City landfill in order to establish the appropriate subgrade for the
temporary and permanent pavement and associated crushed gravel base
courses, including all labor, tools and equipment necessary to complete the
work as specified in these Specifications and as directed by the Engineer.

Board Of Aldermen - Agenda - 4/12/2022 - P198

By dnadmin on Mon, 11/07/2022 - 07:45
  • Read more about Board Of Aldermen - Agenda - 4/12/2022 - P198

Measurement:

The quantity to be measured under ITEM 11C for permanent pavement patch
(Binder and Wearing Courses) shall be measured by the TON based on weight
slips provided on the job site and approved by the Engineer.

Payment:
The approved quantity of hot bituminous pavement for permanent pavement

Board Of Aldermen - Agenda - 4/12/2022 - P197

By dnadmin on Mon, 11/07/2022 - 07:45
  • Read more about Board Of Aldermen - Agenda - 4/12/2022 - P197

Payment:
The accepted quantity of Riprap, Class I shall be paid for at the contract unit

price under ITEM 10, and shall constitute full compensation for furnishing
and placing riprap including geotextile fabric, complete in place as detailed
on the Drawings and as specified, including excavation, backfill, and
disposal of unsuitable materials at the City landfill and all labor, tools, and
equipment necessary to complete the work, and not specifically included for
payment under other items.

2.02 ROADWAY RESTORATION

Board Of Aldermen - Agenda - 4/12/2022 - P196

By dnadmin on Mon, 11/07/2022 - 07:45
  • Read more about Board Of Aldermen - Agenda - 4/12/2022 - P196

The accepted quantity of leaching catch basins constructed shall be paid for
at the contract unit price under ITEM 7C, and shall constitute full
compensation for constructing new leaching catch basin, furnishing and
installing specified frame and grate, complete in place as indicated on the
drawings and/or as specified, including furnishing all materials, labor, tools,
and equipment necessary to complete the work, including but not limited to
excavation, dewatering, backfill, removal of unsuitable materials at the City

Board Of Aldermen - Agenda - 4/12/2022 - P195

By dnadmin on Mon, 11/07/2022 - 07:45
  • Read more about Board Of Aldermen - Agenda - 4/12/2022 - P195

Payment:
The accepted quantity of existing sewer line or drain lateral connections to new

Board Of Aldermen - Agenda - 4/12/2022 - P194

By dnadmin on Mon, 11/07/2022 - 07:45
  • Read more about Board Of Aldermen - Agenda - 4/12/2022 - P194

labor, tools and equipment necessary to complete the work as specified in these
Specifications and as directed by the Engineer.

NOTE:

1. The restoration of the pavement and base course gravels around the frame
and cover shall be paid for separately under the appropriate ROADWAY
RESTORATION contract items.

Pagination