The accepted quantity of leaching catch basins constructed shall be paid for
at the contract unit price under ITEM 7C, and shall constitute full
compensation for constructing new leaching catch basin, furnishing and
installing specified frame and grate, complete in place as indicated on the
drawings and/or as specified, including furnishing all materials, labor, tools,
and equipment necessary to complete the work, including but not limited to
excavation, dewatering, backfill, removal of unsuitable materials at the City
landfill, furnishing and placing stone and geotextile fabric, and all work
incidental thereto and not specifically included for payment under other
items.
P. FLOWABLE FILL FOR PIPE ABANDONED IN PLACE
Measurement:
The quantity of flowable fill for pipe abandoned in place under ITEM 8 will be
measured by the CUBIC YARD based on delivery slips provided on the job
site (minus volume not used) as approved by the Engineer.
Payment:
The accepted quantity of flowable fill for pipe abandoned in place shall be
paid for at the contract unit price under ITEM 8, and shall constitute full
compensation for furnishing and installing flowable fill in the pipe to be
abandoned, complete in place as indicated on the drawings and/or as
specified, including excavation for access to the pipeline, pumping
equipment, backfill, and disposal of unsuitable materials at the City landfill
and all labor, tools, and equipment necessary to complete the work, and not
specifically included for payment under other items.
Q. PRECAST HEADWALL
Measurement:
The quantity of precast headwalls shall be paid for by the EACH under ITEM
9 based on the number of headwalls constructed as approved by the Engineer.
Payment:
The accepted quantity of precast headwalls shall be paid for at the contract
unit price under ITEM 9, and shall constitute full compensation for
furnishing and placing precast headwalls, complete in place as detailed on
the Drawings and as specified, including excavation, backfill, and disposal
of unsuitable materials at the City landfill and all labor, tools, and
equipment necessary to complete the work, and not specifically included for
payment under other items.
R. RIPRAP, CLASS I INCLUDING STONE & GEOXTILE FABRIC)
Measurement:
The quantity of Riprap, Class I shall be paid for by the CUBIC YARD under
ITEM 10 based on the actual volume of riprap placed as approved by the
Engineer.
2022 Sewer Replacement Project Measurement and Payment
Nashua, NH 01150 -9