Payment:
The accepted quantity of trees removed shall be paid for at the contract unit
price under the appropriate subdivisions of ITEM 15 (A thru C) and shall
constitute full compensation for removal of the tree, branches, stump and any
undergrowth within the canopy of the tree, and disposal of all wooded material
off-site in a legal manner, all as specified in these Specifications and as
directed by the Engineer.
Note: The Contractor shall file the /nfent to Cut form, and pay the timber tax
under this Item of work.
M. SILT SACK, SILT FENCE
Measurement:
The quantity of silt sacks to be measured under ITEM 16A will be the actual
number of silt sacks furnished and installed measured by the EACH, complete-
in-place, as specified in these Specifications and as directed by the Engineer.
The quantity of silt fence to be measured under ITEM 16B will be by the
LINEAR FOOT furnished and installed, complete-in-place, as specified in
these Specifications and as directed by the Engineer.
Payment:
The accepted quantity of silt sacks and silt fence shall be paid for at the
contract unit price under ITEM 16A and 16B, and shall be full compensation
for the installation of silt sacks and silt fence including maintenance during the
construction period, and all labor, tools and any other equipment necessary to
complete the work as specified in these Specifications and as directed by the
Engineer.
N. PAVEMENT MARKINGS
Measurement:
The quantity to be measured under the appropriate subdivision of ITEM 17 (A
thru D), shall be measured by the LINEAR FOOT for painted lines, or by the
SQUARE FOOT for painted symbols in accordance with the Contract
Drawings, directions from the Engineer, and as specified herein.
Payment:
The approved quantity of painted lines and painted symbols shall be paid for at
the contract unit price under the appropriate subdivision of ITEM 17 (A thru
D) and shall be full compensation for providing pavement markings including
all labor, tools and any other equipment necessary to complete the work as
specified in these Specifications and as directed by the Engineer.
2.03 PROJECT START-UP AND PROJECT CLOSE OUT:
A. MOBILIZATION
Measurement:
2022 Sewer Replacement Project Measurement and Payment
Nashua, NH 01150 - 14