Skip to main content

Main navigation

  • Documents
  • Search

User account menu

  • Log in
Home
Nashua City Data

Breadcrumb

  1. Home
  2. Board Of Aldermen - Agenda - 4/12/2022 - P194

Board Of Aldermen - Agenda - 4/12/2022 - P194

By dnadmin on Mon, 11/07/2022 - 07:45
Document Date
Fri, 04/08/2022 - 13:45
Meeting Description
Board Of Aldermen
Document Type
Agenda
Meeting Date
Tue, 04/12/2022 - 00:00
Page Number
194
Image URL
https://nashuameetingsstorage.blob.core.windows.net/nm-docs-pages/boa_a__041220…

labor, tools and equipment necessary to complete the work as specified in these
Specifications and as directed by the Engineer.

NOTE:

1. The restoration of the pavement and base course gravels around the frame
and cover shall be paid for separately under the appropriate ROADWAY
RESTORATION contract items.

K. CATCH BASIN CASTING (DOUBLE GRATE)
Measurement:
The quantity to be measured under ITEM 6G shall be by the actual number of
catch basin castings (Double Grate) by the EACH, complete-in-place, as
specified in these Specifications and as directed by the Engineer.

Payment:
The accepted quantity of catch basin castings (See Double Grate Detail on

Plans) shall be paid for at the contract unit price under ITEM 6G, and shall be
full compensation for furnishing and installing double grate catch basin
castings, and all labor, tools and equipment necessary to complete the work as
specified in these Specifications and as directed by the Engineer.

L. CONNECT NEW SEWER OR DRAIN TO EXISTING MANHOLE OR CATCH
BASIN WITH EXISTING HOLE

Measurement:

The quantity to be measured under ITEM 6H will be the actual number of
sewer line connections to existing manholes measured by the EACH,
complete-in-place, as specified in these Specifications and as directed by the
Engineer.

Payment:
The accepted quantity of sewer line connections to existing manholes shall be

paid for at the contract unit price under ITEM 6H, and shall be full
compensation for connecting new sewer line to existing manhole,
modifications to the pipe to manhole joint to form a watertight connection, by-
pass pumping, decanting and disposal of debris at the City landfill and all
labor, tools and any other equipment necessary to complete the work as
specified in these Specifications and as directed by the Engineer.

M. CONNECT EXISTING SEWER LINE OR DRAIN LATERAL TO NEW
MANHOLE OR CATCH BASIN
Measurement:
The quantity to be measured under ITEM OI will be the actual number of
connections of existing sewer lines or drain laterals of any size up to 18-inch
diameter to new manholes measured by the EACH, complete-in-place, as
specified in these Specifications and as directed by the Engineer.

2022 Sewer Replacement Project Measurement and Payment