  2. Board Of Aldermen - Agenda - 4/12/2022 - P198

Board Of Aldermen - Agenda - 4/12/2022 - P198

By dnadmin on Mon, 11/07/2022 - 07:45
Document Date
Fri, 04/08/2022 - 13:45
Meeting Description
Board Of Aldermen
Document Type
Agenda
Meeting Date
Tue, 04/12/2022 - 00:00
Page Number
198
Image URL
https://nashuameetingsstorage.blob.core.windows.net/nm-docs-pages/boa_a__041220…

Measurement:

The quantity to be measured under ITEM 11C for permanent pavement patch
(Binder and Wearing Courses) shall be measured by the TON based on weight
slips provided on the job site and approved by the Engineer.

Payment:
The approved quantity of hot bituminous pavement for permanent pavement

patch shall be paid for at the contract unit price for ITEM 11C and shall be full
compensation for the furnishing, placing, compacting hot mix asphalt
pavement by methods approved by the Engineer, including all labor, tools and
any other equipment necessary to complete the work as specified in these
Specifications and as directed by the Engineer.

Notes:

1. Permanent pavement course thicknesses shall be as specified
on the plans, or as ordered by the Engineer.

2. Tack coats shall be applied between all pavement courses and
shall be incidental to this item of work and not measured
separately for payment.

3. Replacement of pavement markings are paid for under
ITEMS 17 (A thru D).

D. SAWED BITUMINOUS PAVEMENT
Measurement:
The quantity to be measured under ITEM 11D, Sawed Bituminous Pavement,
shall be measured by the LINEAR FOOT in accordance with the Contract
Drawings, directions from the Engineer, and as specified herein.

Payment:

The approved quantity of sawed bituminous pavement shall be paid for at the
contract unit price for ITEM 11D and shall be full compensation for saw
cutting bituminous pavement of any depth, including all labor, tools and any
other equipment necessary to complete the work as specified in these
Specifications and as directed by the Engineer.

E. UNCLASSIFIED EXCAVATION

Measurement:

The quantity to be measured under ITEM 11E shall be measured per CUBIC
YARD in place. Measurement for payment of this item shall only apply to the
unclassified excavation for the placement of temporary and permanent
pavement, sidewalk areas and associated crushed gravel to the depths specified
in the contract drawings. Quantities shall be measured for payment as directed
and approved by the Engineer. Over-excavated trenches will not be allowed.

Payment:
The approved quantity of unclassified excavation shall be paid for at the
contract unit price for ITEM 11E and shall be full compensation for the

2022 Sewer Replacement Project Measurement and Payment
Nashua, NH 01150 - 11