Finance Committee - Agenda - 3/17/2021 - P44
SUMMARY OF LABOR AND COSTS - DRAFT
CITY OF NASHUA, NH
SIPHON REHABILITATION - DESIGN & BIDDING
HAZEN AND SAWYER TEAM BUDGET FOR TASK B2 - Bid Phase Services
TOTAL
TOTAL LABOR &
OTHER
SUMMARY OF LABOR AND COSTS - DRAFT
CITY OF NASHUA, NH
SIPHON REHABILITATION - DESIGN & BIDDING
HAZEN AND SAWYER TEAM BUDGET FOR TASK B2 - Bid Phase Services
TOTAL
TOTAL LABOR &
OTHER
Draft Drawing List and Bid Set LOE
City of Nashua
Siphon Rehabilitation
Submittal Percentages of Total Hours
SUMMARY OF LABOR AND COSTS - DRAFT
CITY OF NASHUA, NH
SIPHON REHABILITATION - DESIGN & BIDDING
HAZEN AND SAWYER TEAM BUDGET FOR TASK B1 - Design Services for Siphon Rehabilitation
SUMMARY OF LABOR AND COSTS - DRAFT
CITY OF NASHUA, NH
SIPHON REHABILITATION - DESIGN & BIDDING
SUMMARY OF LABOR AND COSTS - DRAFT 10/16/20
CITY OF NASHUA, NH
SIPHON REHABILITATION - DESIGN & BIDDING
HAZEN AND SAWYER TEAM BUDGET BY TASK
EXHIBITC
City of Nashua, NH
Siphon Rehabilitation
Scope of Work for Engineering Design and Construction Phase Services
B2.7 Provide written recommendations and evaluations of the three lowest general bidders. Include
whether or not the bidders have the skill, ability and integrity to perform the work required for the Project
based on a determination of competent workmanship and financial soundness. Provide a written
recommendation to award the construction contract to the lowest responsible and eligible general bidder.
City of Nashua, NH
Siphon Rehabilitation
Scope of Work for Engineering Design and Construction Phase Services
B1.2 Field Investigations
City of Nashua, NH
Siphon Rehabilitation
Scope of Work for Engineering Design and Construction Phase Services
Table 2 Summary of Recommended Siphon Rehabilitation
Name Size Material Rehab Siphon Comment
(in) Recommendation QSR
CSO 6 18 RCP CIPP 2813 CIPP for cracks, visible aggregate
Trestle
Bridge
Canal St 10 Cl CIPP 3121 Install full length CIPP due to erosion of cement
Parking liner.
City of Nashua, NH
Siphon Rehabilitation
Scope of Work for Engineering Design and Construction Phase Services
A. Project Administration, Meetings, and Quality Assurance/Quality Control
Al Project Management
February 2021 EXHIBIT B
City of Nashua, NH
Siphon Rehabilitation
Scope of Work for Engineering Design Services
Background
During the Phase 1 of the City’s CMOM program the City’s eight inverted siphons were cleaned and inspected.
The siphons were constructed between the 1960’s and the early 1980’s. Six siphons are triple-barrel and two are
double-barrel comprised of various materials and diameters ranging from 6 inches to 60 inches in diameter.
Below is an inventory of the siphons inspected:
Table 1 Inventory of Siphons Inspected