Finance Committee - Agenda - 6/7/2017 - P487

By dnadmin on Mon, 11/07/2022 - 10:24
  • Read more about Finance Committee - Agenda - 6/7/2017 - P487

E.

01800-2
EQUIPMENT/ SYSTEM TESTING CERTIFICATION

Schedules:

1. The Pre-Startup Meeting shall be held at least ten (10) working days prior to
the startup of the first piece of equipment supplied under the Contract. At that
time, the Contractor shall present his plan as detailed in the previous Part D
"Submittals" and review Engineer's comments and concerns associated with
the general features of each piece of equipment which must be demonstrated.

Finance Committee - Agenda - 6/7/2017 - P486

By dnadmin on Mon, 11/07/2022 - 10:24
  • Read more about Finance Committee - Agenda - 6/7/2017 - P486

01800-1

SECTION 01800

EQUIPMENT STARTUP, CERTIFICATION AND OPERATOR TRAINING

PART 1 - GENERAL

1.1

DESCRIPTION
A. Work Included:

1.

Finance Committee - Agenda - 6/7/2017 - P485

By dnadmin on Mon, 11/07/2022 - 10:24
  • Read more about Finance Committee - Agenda - 6/7/2017 - P485

01720-4
PROJECT RECORD DOCUMENTS

3. Title and number of each record document with certification that each
document is completed and accurate.

4. Signature of Contractor, or his authorized representative.

Failure to supply all information on the Project Record Drawings as specified in

Part 1.3 may result in additional retainage from monthly partial payment requests,

and in non-approval of final payments of the Contract and/or if contract time (as

specified in accordance with the Standard General Conditions of the Construction

Finance Committee - Agenda - 6/7/2017 - P484

By dnadmin on Mon, 11/07/2022 - 10:24
  • Read more about Finance Committee - Agenda - 6/7/2017 - P484

01720-3
PROJECT RECORD DOCUMENTS

6. Roads

a. Show centerline road profile and level spot elevations.

b. Show pavement widths.

c. Onroad cross sections, show the pavement cross slope.

d. Show any deviations from the design plans.

7. Buildings

a. In general, small changes to structures should not be redrawn. If any
dimensional changes were made in the field, the numerical change
should be made on the Drawing and be properly labeled. Update
dimensions and elevations on Drawings.

Finance Committee - Agenda - 6/7/2017 - P483

By dnadmin on Mon, 11/07/2022 - 10:24
  • Read more about Finance Committee - Agenda - 6/7/2017 - P483

01720-2
PROJECT RECORD DOCUMENTS

Existing Utilities

a. Water mains and services, water main gate valves, sewer mains and
services, storm drains, culverts, steam lines, gas lines, tanks and other
existing utilities encountered during construction must be accurately
located and shown on the Drawings. In congested areas supplemental
drawings or enlargements may be required.

Finance Committee - Agenda - 6/7/2017 - P482

By dnadmin on Mon, 11/07/2022 - 10:24
  • Read more about Finance Committee - Agenda - 6/7/2017 - P482

SECTION 01720

PROJECT RECORD DOCUMENTS

PART | - GENERAL

1.1

1.2

1.3

DESCRIPTION
A. Work Included:
1. Keep accurate record documents for all additions, substitutions of material,
variations in work, and any other additions or revisions to the Contract.
B. Related Work Specified Elsewhere:
1. Shop Drawings, Project Data, and Samples are specified in "General
Conditions" and Section 01340, Submittals.

MAINTENANCE OF DOCUMENTS
A. Maintain at job site, one copy of:

1. Contract Drawings

Finance Committee - Agenda - 6/7/2017 - P481

By dnadmin on Mon, 11/07/2022 - 10:24
  • Read more about Finance Committee - Agenda - 6/7/2017 - P481

01710-2
PROJECT CLEANING

Control of Hazards:

1. Store volatile wastes in covered metal containers, and remove from premises
daily.

2. Prevent accumulation of wastes which may create hazardous conditions.

3. Provide adequate ventilation during use of volatile or noxious substances.

Disposal:

1. Donot burn or bury rubbish and waste materials on project site.

2. Donot dispose of volatile wastes, such as mineral spirits, oil, or paint thinner, in
storm or sanitary drains.

Finance Committee - Agenda - 6/7/2017 - P480

By dnadmin on Mon, 11/07/2022 - 10:24
  • Read more about Finance Committee - Agenda - 6/7/2017 - P480

01710-1

SECTION 01710

PROJECT CLEANING

PART 1 - GENERAL

1.1 DESCRIPTION
A. Work Included:

1.

2.

Maintain premises and public properties free from accumulations of waste,
debris, and rubbish, caused by operations.

At completion of work, remove waste materials, tools, equipment, machinery
and surplus materials, and clean all sight-exposed surfaces. Leave project clean
and ready for use.

1.2 QUALITY ASSURANCE

Finance Committee - Agenda - 6/7/2017 - P479

By dnadmin on Mon, 11/07/2022 - 10:24
  • Read more about Finance Committee - Agenda - 6/7/2017 - P479

01630-1
SECTION 01630

SUBSTITUTIONS & PRODUCT OPTIONS

PART 1 - GENERAL

1.1

1.2

1.3

1.4

DESCRIPTION

A.

The below listed requirements are in addition to the requirements contained in the
General Conditions, Articles 8.3 - 8.5.

SUBMITTALS

A.

B.

Submit a written application for approval completely describing the proposed
substitution.

Submit, when requested by the Engineer:

1. Manufacturer's catalog data.

Illustrations.

Specifications.

Finance Committee - Agenda - 6/7/2017 - P478

By dnadmin on Mon, 11/07/2022 - 10:24
  • Read more about Finance Committee - Agenda - 6/7/2017 - P478

01590-1
SECTION 01590

TEMPORARY FIELD OFFICE

PART | - GENERAL

1.1 DESCRIPTION
A. Work Included: Provide and maintain office supplies and equipment for the
exclusive use of the Engineer during the entire life of the Contract.

PART 2 - PRODUCTS

2.1 PRODUCTS