assigned by Professional Engineer to perform work under this contract. Approved key
personnel shall not be taken off of the project by Professional Engineer without the prior
written approval of the City of Nashua, except in the event of termination of employment.
Professional Engineer shall, if requested to do so by the City of Nashua, remove from the
job any personnel whom the City of Nashua determines to be incompetent, dishonest, or
uncooperative.
CITY OF NASHUA REPRESENTATIVE The City of Nashua may designate a City of Nashua
representative for this contract. If designated, all notices, project materials, requests by
Professional Engineer, and any other communication about the contract shall be addressed
or be delivered to the City of Nashua Representative.
CHANGES TO SCOPE OF WoRK The City of Nashua may, at any time, by written order,
make changes to the general scope, character, or cost of this contract and in the services or
work to be performed, either increasing or decreasing the scope, character, or cost of
Professional Engineer's performance under the contract. Professional Engineer shall
provide to the City of Nashua within 10 calendar days, a written proposal for accomplishing
the change. The proposal for a change shall provide enough detail, including personnel
hours for each sub-task and cost breakdowns of tasks, for the City of Nashua to be able to
adequately analyze the proposal. The City of Nashua will then determine in writing if
Professional Engineer should proceed with any or all of the proposed change. Ifthe change
causes an increase or a decrease in Professional Engineer's cost or time required for
performance of the contract as a whole, an equitable adjustment shall be made and the
contract accordingly modified in writing. Any claim of Professional Engineer for
adjustment under this clause shall be asserted in writing within 30 days of the date the City
of Nashua notified Professional Engineer of the change.
When Professional Engineer seeks changes, Professional Engineer shall, before any work
commences, estimate their effect on the cost of the contract and on its schedule and notify
the City of Nashua in writing of the estimate. The proposal for a change shall provide
enough detail, including personnel hours for each sub-task and cost breakdowns of tasks,
for the City of Nashua to be able to adequately analyze the proposal. The City of Nashua
will then determine in writing if Professional Engineer should proceed with any or all of
the proposed change.
Except as provided in this paragraph, Professional Engineer shall implement no change
unless the City of Nashua in writing approves the change. Unless otherwise agreed to in
writing, the provisions of this contract shall apply to all changes. The City of Nashua may
provide verbal approval of a change when the City of Nashua, in its sole discretion,
determines that time is critical or public health and safety are of concern. Any verbal
approval shall be confirmed in writing as soon as practicable. Any change undertaken
without prior City of Nashua approval shall not be compensated and is, at the City of
Nashua's election, sufficient reason for contract termination.
Ciry OF NASHUA COOPERATION The City of Nashua agrees that its personnel will
cooperate with Professional Engineer in the performance of its work under this contract
and that such personnel will be available to Professional Engineer for consultation at
reasonable times and after being given sufficient advance notice that will prevent conflict
with their other responsibilities. The City of Nashua also agrees to provide Professional
GC 3 of 13