Board Of Aldermen - Agenda - 8/11/2020 - P118
4 7 led T 181 Pearl Siveat end Figor
Touloukian Touloukian Inc. Boston MA 02170
Acohitecture + Urban Desian T+1 547 528 0884
ww torch com
27 July 2020
Greg Bakos, Principal Engineer
VHB
99 High Street,
10th Flocr. -.
Bosion, MA 02710
Re: Nashua Riverfront Parc ce la Renaissance Pavilion Project
cc: Bob Uhlig — Halvorson Tighe & Bond Studio (HTB)
Piease find below an cutline of services and fees jor your review. Information provided is based
on limited understanding of the site and its requirements.
Part |: Existing Conditions and Proposed Site Flan:
e Client and its consultanis are to provide existing site plan with geo technical report, and
proposed site pian. Client to provide site files in CAD and pdf with urban context in 3D
skeich up.
« TT to review documenis, and include files in Part ll conceptual design studies.
Part li: Concepiual Design: (Estimated Schedule 2-3 mos’.
e First Meeting: Based on HTB March 2020, Site Plan A-Concept plan, TT will provide (2)
design variations for review with the City and design team. Presentation will include 3D
sketch up models, precedent images, and conceptual site plan.
e Second Meeting: Based on one preferred direction from the meeting above, TT to
develop (1) design option and provide revised presentation that Includes 3D sketch up
models, precedent images and conceptual site plan.
Part Ill: Desion Develooment/Consitruction Documents (Estimated Schedule 3-4 mos):
» Provide construction documents for the preferred design option above.
e include structural engineering drawings and speciiications with bid submission.
e Include (2} meetings with the Client io review progress. Include 100% DD set, 90% CD
progress sets, and Bid Set submission.
Part IV: Other:
e Design assumes conventional concrete spread footing and foundation wail structure set
max below grade at frost line and not submerged inte the water. Geo-technical report by
others.
Includes conventional ambient jighting. Does not include stage lighting or rigging. Lighting
design and electrical engineer by others.
Open air structure with no wails, and roof with louvers.
Front end specifications (conventionally Division 0 and 1} by others.
Construction Cost estimate by others. TT understands that the construction cost budget
is estimated at 500-550k max. Increase in approved costs may reflect a change in fee.
» LEED services not included and can be provided as an additional service.
e
Pari V: Fees
*» Fee is estimated ai $119,000 which includes $42,500 for Part | and ||, and $78,500 for
Part lll. Fee includes allowance of 12.5k for structural engineer and allowance of 3.0k for
CSI specifications. includes an allowance of 1.0k for reimbursables.
« Schedule is understoed to have work completed continuously within 6 mos.
» Fee is good for 30 days after date of submission.
Sincerely,
Touloukian Touloukian inc., Theodore Touloukian, AIA, As President