Finance Committee - Agenda - 12/26/2017 - P38
Safe routes to School Birch Hill Elementary
BID SCHEDULE
Variable Message Radar Speed Feedback Signs on Dublin Avenue
Safe routes to School Birch Hill Elementary
BID SCHEDULE
Variable Message Radar Speed Feedback Signs on Dublin Avenue
To:
From:
Re:
C. Motion:
Attachment:
Discussion:
City of Nashua, Public Works Division
Board of Public Works Meeting Date: December 14, 2017
Wayne R. Husband, Senior Traffic Engineer
Public Works Administration
Speed Radar Feedback Signs at Birch Hill Elementary School
THE CITY OF NASHUA “the Cate City’
Financial Services
Purchasing Department
December 14, 2017
Memo #18-064
TO: MAYOR DONCHESS
FINANCE COMMITTEE
SUBJECT: | SPEED RADAR FEEDBACK SIGNS AT BIRCH HILL ELEMENTARY SCHOOL (VALUE:
$28,220)
DEPARTMENT: 160 ENGINEERING; FUNDS: GRANT SAFE ROUTES TO SCHOOL
$17,920 AND QUADRANT TRUST FUNDS $10,300
Please see the attached communication from Stephen Dookran, P.E., City Engineer, dated December 14,
2017 for information related to this purchase.
£ : Hayner/Swanson, Inc.
Civil Engineers/Land Surveyors
BA
December 5, 2017
Ms. Lisa Fauteux
Director of Public Works
9 Riverside Street
Nashua, NH 03062
Dear Ms. Fauteux:
To:
From:
Re:
E. Motion:
Discussion:
City of Nashua, Public Works Division
Board of Public Works Meeting Date: December 14, 2017
Stephen Dookran, P.E., City Engineer
Engineering Department
Pavement Management (Engineering Services)
Change Order 1
To approve Change Order No. 1 of the engineering contract with Hayner/Swanson, Inc.
of Nashua, NH in the amount of $40,000. Funding will be through multi-year paving
project. Department: 160 Admin/Engineering; Fund: Bond; Activity: Paving
BOs SE ~~
foe te
Ys ks "
Ad Aad
Hb
i is > “|
n ee
88
THE CITY OF NASHUA “The Cate City"
Financial Services
Purchasing Department
December 14, 2017
Memo #18-063
TO: MAYOR DONCHESS
FINANCE COMMITTEE
SUBJECT: HAYNER/SWANSON — PAVEMENT MANAGEMENT (ENGINEERING SERVICES)
CHANGE ORDER 1 (VALUE: $40,000)
DEPARTMENT: 160 ADMIN/ENGINEERING; FUND: BOND
CLD Consulting Engineers
17 February 2017
Page 4
We appreciate the opportunity to submit this proposal and look forward to our association with youon
this project. Please contact the undersigned if you wish to discuss this proposal or any aspect of the
project.
Sincerely yours,
HALEY & ALDRICH, INC.
Bet ob be
John G. DiGenova, P.E.
Associate
Senior Geotechnical Engineer
G:\129653_Canal Street Bridge\Deliverables\2016-0830-HAI-Geotechnical Proposal Canal Street Bridge-F.docx
CLD Consulting Engineers
17 February 2017
Page 3
Tesi borings are completed within three rig-days. if subsurface conditions are unfavorable
(obstructions, difficult drilling, access problems, frozen ground, snow banks, or other unforeseen
problems), additional exploration time may be required at additional cost. We would inform
you of exploration progress issues, and obtain your authorization prior to undertaking additional
rig-days or exploration work.
®
CLD Consulting Engineers
17 February 2017
Page 2
coring to drill through obstructions, if encountered. Borehoies will be backfilled with drill
cuttings and grout at the ground surface. Boreholes will not be left open overnight without
protection.
HALEY & ALDRICH, INC.
3 Bedford Farms Drive
Bedford, NH 03110
603.625.5353
17 February 2017
File No. 129653-001
CLD Consulting Engineers, inc.
540 Commercial Street
Manchester, NH 03101
Attention: Mr. John Byatt
Structures Team Leader
Subject: Geotechnical Engineering Services
Canal Street Bridge
Nashua, NH
Dear Mr. Byatt:
Haley & Aldrich is pleased to submit this proposal for engineering services in connection with the subject
project. Thank you for this opportunity.