16010-5
ELECTRICAL - GENERAL

Secure and pay for all permits, fees and licenses necessary for the proper
execution of the work under DIVISION 16.

Tests and Procedures Prior To Start-up:

Refer to Section 16950 - Testing Electrical Systems and start-up for testing and
scheduling requirements.

Demonstration of Complete Electrical Systems:

1.

2.
Iden
1.

Finance Committee - Agenda - 6/7/2017 - P611

By dnadmin on Mon, 11/07/2022 - 10:24
  • Read more about Finance Committee - Agenda - 6/7/2017 - P611

5.

1.

16010-4
ELECTRICAL - GENERAL

required to modify these changes along with all requirements for installation
of the new work, as shown on the Contract Drawings.

Finance Committee - Agenda - 6/7/2017 - P610

By dnadmin on Mon, 11/07/2022 - 10:24
  • Read more about Finance Committee - Agenda - 6/7/2017 - P610

16010-3
ELECTRICAL - GENERAL

e. Provide complete branch circuit wiring systems including all raceways,
conductors, cables, outlet and junction boxes, wiring devices and device
connections as shown on the Drawings and as specified herein.

G. Work Specified Elsewhere:

1.

2.

The materials and methods used for all Electrical Work indicated in the
Contract Documents shall meet the requirements specified in Division 16.

Finance Committee - Agenda - 6/7/2017 - P609

By dnadmin on Mon, 11/07/2022 - 10:24
  • Read more about Finance Committee - Agenda - 6/7/2017 - P609

16010-2
ELECTRICAL - GENERAL

F. Work Specified Herein:

1.

Visit and examine the project site and become familiar with all existing
conditions pertinent to the work to be performed thereon. No additional
compensation will be allowed for failure to be so informed. This contractor is
responsible to be familiarized with the conditions of the project during the
bidding period in order to bring any clarifications or issues to the attention of
the Engineer prior to submission of his/her final bid price.

Finance Committee - Agenda - 6/7/2017 - P608

By dnadmin on Mon, 11/07/2022 - 10:24
  • Read more about Finance Committee - Agenda - 6/7/2017 - P608

16010-1
SECTION 16010

ELECTRICAL - GENERAL

PART 1 - GENERAL

1.1

DESCRIPTION

A.

Provide all labor, materials, equipment, operations, methods and procedures as
indicated in the Contract Documents, together with all items necessary for or
incidental to the completion of the work.

All systems or additions to existing systems indicated in the Contract Documents

shall mean all necessary supervision, labor, equipment and materials required to

provide complete, properly functioning systems.

Finance Committee - Agenda - 6/7/2017 - P607

By dnadmin on Mon, 11/07/2022 - 10:24
  • Read more about Finance Committee - Agenda - 6/7/2017 - P607

vo

15907-7
TESTING AND BALANCING HEATING AND VENTILATING SYSTEMS

selections of data (water and air quantities and air motion) recorded in the Certified
Report.

Points and areas for recheck will be selected by the Engineer.

Measurement and test procedures shall be the same as approved by the Engineer for
the Work forming basis of report.

Selections for recheck (specific plus random), in general, will not exceed 15 percent
of the total number tabulated in the report.

Finance Committee - Agenda - 6/7/2017 - P606

By dnadmin on Mon, 11/07/2022 - 10:24
  • Read more about Finance Committee - Agenda - 6/7/2017 - P606

15907-6
TESTING AND BALANCING HEATING AND VENTILATING SYSTEMS

iii. Type Drive.
iv. Motor H.P., Voltage, Phase, and Full Load Amps.
b. Design Data:

i. G.P.M.
ii. Head.
iii RPM.

Finance Committee - Agenda - 6/7/2017 - P605

By dnadmin on Mon, 11/07/2022 - 10:24
  • Read more about Finance Committee - Agenda - 6/7/2017 - P605

15907-5
TESTING AND BALANCING HEATING AND VENTILATING SYSTEMS

Finance Committee - Agenda - 6/7/2017 - P604

By dnadmin on Mon, 11/07/2022 - 10:24
  • Read more about Finance Committee - Agenda - 6/7/2017 - P604

3.3

3.4

3.5

oA

M.

15907-4
TESTING AND BALANCING HEATING AND VENTILATING SYSTEMS

elbows, bends, take-offs, and other turbulence generating devices, to optimize
reliability of flow measurements.

Air Terminal Balancing.

Air Motion: Air motion and distribution shall be as specified and as shown on
Drawings. In addition to air motion measurements, make smoke tests wherever
requested by the Engineer, to demonstrate the air distribution from air terminals, at
no additional cost to the Owner.

Finance Committee - Agenda - 6/7/2017 - P603

By dnadmin on Mon, 11/07/2022 - 10:24
  • Read more about Finance Committee - Agenda - 6/7/2017 - P603

3.2

15907-3
TESTING AND BALANCING HEATING AND VENTILATING SYSTEMS

Apply all instruments in accordance with manufacturer's instructions and
recommendations.

Provide all labor, instruments and appliances required. Do not install instruments
that are permanent installations used for the tests, e.g., gages, thermometers, etc.,
until just prior to the tests to avoid damage and changes in calibration.