12. The following which may be delivered or issued on or after the Effective Date of the
Agreement and are not attached hereto:

a. Written Amendments
b. Change Order(s)

14. New Hampshire Department of Transportation “Standard Specifications for Road and

Bridge Construction”, latest edition, incorporated by reference or unless otherwise
indicated.

15 “Manual of Uniform Traffic Control Devices”, latest edition, incorporated by reference.

Finance Committee - Agenda - 5/16/2018 - P301

By dnadmin on Mon, 11/07/2022 - 11:42
  • Read more about Finance Committee - Agenda - 5/16/2018 - P301

G. CONTRACTOR does not consider that any further examinations, investigations,
explorations, tests, studies, or data are necessary for the performance of the Work at the Contract Price, within
the Contract Times, and in accordance with the other terms and conditions of the Contract Documents.

H. CONTRACTOR is aware of the general nature of work to be performed by OWNER and
others at the Site that relates to the Work as indicated in the Contract Documents.

Finance Committee - Agenda - 5/16/2018 - P300

By dnadmin on Mon, 11/07/2022 - 11:42
  • Read more about Finance Committee - Agenda - 5/16/2018 - P300

3. After the work is 50% complete, and provided the CONTRACTOR has satisfied the
ENGINEER in quality and timeliness of the work, and provided further that there is
no specific cause for withholding additional retainage no further amount will be

remainder of the project.
6.03 Final Payment

A. Upon final completion and acceptance of the Work in accordance with paragraph 14.07 of the
General Conditions, OWNER shall hold 2% retainage during the 1 (one) year warranty period and release it
only after the project has been accepted.

Finance Committee - Agenda - 5/16/2018 - P299

By dnadmin on Mon, 11/07/2022 - 11:42
  • Read more about Finance Committee - Agenda - 5/16/2018 - P299

ARTICLE 6 - PAYMENT PROCEDURES
6.01 Submittal and Processing of Payments

A. CONTRACTOR shall submit Applications for Payment in accordance with Article 14 of the
General Conditions. Applications for Payment will be processed by ENGINEER as provided in the General
Conditions.

B. Applications for Payment under this agreement shall be submitted as follows:
> Electronically via email to VendorAPInvoices@NashuaNH.gov
OR

> Paper Copies via US Mail to:

Finance Committee - Agenda - 5/16/2018 - P298

By dnadmin on Mon, 11/07/2022 - 11:42
  • Read more about Finance Committee - Agenda - 5/16/2018 - P298

4.02 Dates for Substantial Completion

A. Project will begin once a written “Notice to Proceed” is issued.
B. Substantial Completion shall be 715 calendar days from the Notice to Proceed and
Final Completion shall be __90 calendar days from the Notice to Proceed,

4.03 Liquidated Damages

Finance Committee - Agenda - 5/16/2018 - P297

By dnadmin on Mon, 11/07/2022 - 11:42
  • Read more about Finance Committee - Agenda - 5/16/2018 - P297

STANDARD FORM OF AGREEMENT
BETWEEN OWNER AND CONTRACTOR

THIS AGREEMENT is dated as of the __ day of in the year 2018 by and between the City
of Nashua, New Hampshire (hereinafter called OWNER) and Layne Inliner, LLC and its successors,
transferees and assignees together (hereinafter called CONTRACTOR).

OWNER and CONTRACTOR, in consideration of the mutual covenants hereinafter set forth, agree as
follows:

ARTICLE 1 - WORK

Finance Committee - Agenda - 5/16/2018 - P296

By dnadmin on Mon, 11/07/2022 - 11:42
  • Read more about Finance Committee - Agenda - 5/16/2018 - P296

To:

From:

Re:

G. Motion:

Discussion:

City of Nashua, Public Works Division

Board of Public Works Meeting Date: April 26, 2018

Stephen Dookran, P.E., City Engineer
Engineering Department

2018 CIPP Lining
Construction

To approve the construction contract for the 2018 CIPP Lining to Layne Inliner of
Fairfield, ME in the amount of $715,657.50. Funding will be through: Department: 169
Wastewater; Fund: Bond; Activity: Sewer Rehab.

Finance Committee - Agenda - 5/16/2018 - P295

By dnadmin on Mon, 11/07/2022 - 11:42
  • Read more about Finance Committee - Agenda - 5/16/2018 - P295

2)\ THE CITY OF NASHUA The Gate City’

Financtal Services

Purchasing Department

a: 7 Se a

May 10, 2018
Memo #18-124

TO: MAYOR DONCHESS
FINANCE COMMITTEE

SUBJECT: 2018 CIPP LINING (VALUE: $715,658)
DEPARTMENT: 169 WASTEWATER; FUND: BOND

Please see the attached communication from Stephen Dookran, P.E., City Engineer, dated April 26, 2018
for information related to this purchase.

Finance Committee - Agenda - 5/16/2018 - P294

By dnadmin on Mon, 11/07/2022 - 11:42
  • Read more about Finance Committee - Agenda - 5/16/2018 - P294

Bid Tabulation
2019 Landfill Gas System Expansion
Four Hills Landfill

Nashua, New Hampshire

__EnviroTrac, Ltd.

Northeast Earth Mechanics

Finance Committee - Agenda - 5/16/2018 - P293

By dnadmin on Mon, 11/07/2022 - 11:42
  • Read more about Finance Committee - Agenda - 5/16/2018 - P293

Bid Tabulation

2019 Landfill Gas System Expansion
Four Hills Landfill

Nashua, New Hampshire