  2. Finance Committee - Agenda - 5/16/2018 - P300

Finance Committee - Agenda - 5/16/2018 - P300

By dnadmin on Mon, 11/07/2022 - 11:42
Document Date
Wed, 05/16/2018 - 00:00
Meeting Description
Finance Committee
Document Type
Agenda
Meeting Date
Wed, 05/16/2018 - 00:00
Page Number
300
Image URL
https://nashuameetingsstorage.blob.core.windows.net/nm-docs-pages/fin_a__051620…

3. After the work is 50% complete, and provided the CONTRACTOR has satisfied the
ENGINEER in quality and timeliness of the work, and provided further that there is
no specific cause for withholding additional retainage no further amount will be

remainder of the project.
6.03 Final Payment

A. Upon final completion and acceptance of the Work in accordance with paragraph 14.07 of the
General Conditions, OWNER shall hold 2% retainage during the 1 (one) year warranty period and release it
only after the project has been accepted.

ARTICLE 7 - CONTRACTOR'S REPRESENTATIONS

7.01 In order to induce OWNER to enter into this Agreement CONTRACTOR makes the following
representations:

A. CONTRACTOR has examined and carefully studied the Contract Documents and the other
related data identified in the Bidding Documents.

B. CONTRACTOR has visited the Site and become familiar with and is satisfied as to the
general, local, and Site conditions that may affect cost, progress, and performance of the Work.

C. CONTRACTOR is familiar with and is satisfied as to all federal, state, and local Laws and
Regulations that may affect cost, progress, and performance of the Work.

D. CONTRACTOR has carefully studied all (if any): (1) reports of explorations and tests of
subsurface conditions at or contiguous to the Site and all drawings of physical conditions in or relating to
existing surface or subsurface structures at or contiguous to the Site (except Underground Facilities) which
have been identified in the Supplementary Conditions as provided in paragraph 4.02 of the General
Conditions and (2) reports and drawings of Hazardous Environmental Condition, if any, at the Site which has
been identified in the Supplementary Conditions as provided in paragraph 4.06 of the General Conditions.

E. CONTRACTOR is entitled to rely upon the general accuracy of the “technical data” as
provided in paragraph 4.2 of the General Conditions. CONTRACTOR acknowledges that such reports and
drawings are not Contract Documents and may not be complete for CONTRACTOR's purposes.
CONTRACTOR acknowledges that OWNER and ENGINEER do not assume responsibility for the
accuracy or completeness of information and data shown or indicated in the Contract Documents with
respect to Underground Facilities at or contiguous to the site.

F, CONTRACTOR has obtained and carefully studied (or assumes responsibility for having
done so) all additional or supplementary examinations, investigations, explorations, tests, studies, and data
concerning conditions (surface, subsurface and Underground Facilities) at or contiguous to the Site which
may affect cost, progress, or performance of the Work or which relate to any aspect of the means, methods,
techniques, sequences and procedures of construction, if any, expressly required by the Contract Documents
to be employed by CONTRACTOR, and safety precautions and programs incident thereto.

AG - 4 0f 8