G. CONTRACTOR does not consider that any further examinations, investigations,
explorations, tests, studies, or data are necessary for the performance of the Work at the Contract Price, within
the Contract Times, and in accordance with the other terms and conditions of the Contract Documents.
H. CONTRACTOR is aware of the general nature of work to be performed by OWNER and
others at the Site that relates to the Work as indicated in the Contract Documents.
I. CONTRACTOR has correlated the information known to CONTRACTOR, information
and observations obtained from visits to the Site, reports and drawings identified in the Contract Documents
and all additional examinations, investigations, explorations, tests, studies, and data with the Contract
Documents.
J. CONTRACTOR has given ENGINEER written notice of all conflicts, errors, ambiguities or
discrepancies that CONTRACTOR has discovered in the Contract Documents, and the written resolution
thereof by ENGINEER is acceptable to CONTRACTOR.
K. The Contract Documents are generally sufficient to indicate and convey understanding of all
terms and conditions for performance and furnishing of the Work.
ARTICLE 8 - CONTRACT DOCUMENTS
8.01 Contents
A. The Contract Documents consist of the following:
1. This Agreement;
2. General Conditions;
3. Supplementary Conditions;
4. Bid Bond;
5. Bid Form;
6. Performance Bond;
7. Payment Bond;
8. Certificate of Insurance
9. Technical Specifications as listed in Table of Contents
10. Addenda (numbers 1 to 1_, inclusive);
11. Exhibits, as listed in the Table of Contents, to this Agreement
AG -50f8