Board Of Aldermen - Agenda - 6/14/2022 - P87
The H.L. Turner Group Inc.
SSS EEE ——,
27 Locke Road Concord, NH 03301
: 603.228.1122 hiturner.com
Nashua Riverfront Development Project
Final Engineering Design
The H.L. Turner Group Inc.
SSS EEE ——,
27 Locke Road Concord, NH 03301
: 603.228.1122 hiturner.com
Nashua Riverfront Development Project
Final Engineering Design
The H.L. Turner Group Inc.
27 Locke Road Concord, NH 03301 = t: 603.228.1122 hiturner.com
Nashua Riverfront Development Project
Final Engineering Design
The H.L. Turner Group Inc.
27 Locke Road Concord, NH 03301
:603.228.1122 hiturner.com
Nashua Riverfront Development Project
Final Engineering Design
“Bas
Attachment A
Fee Summary Sheet
ic’ and “Additional” Services
Final Engineering Design
Item Fees
1. Basic Design ServiceS........ccssserssseccsssersseesssisereseriseeneneeteseonsscesreeeensestaee ..5286,340.00
2. Additional Services:
Al Geotechnical Analyses & Recommendation. ......cscccsseseesseceesees §$ 75,000.00
A.2 —_ Spot Field SUrVEYS......cscescressssssesreersessstsstesserentesstersesssetserteeenertts § 12,000.00
A3 Project Progress Meetings.........cccccsssscecsesnssseeseeesnarssensenseneees § 16,000.00
Attachment A
Fee Summary Sheet
CONTRACT FORM
Please sign and return these originals as your acceptance of the above scope and terms,
including noted attachments, and your authorization to proceed. Please also provide a
purchase order or equivalent accounting number, if applicable, at the end of this letter in
order to allow us to proceed.
CLIENT RESPONSIBILITIES
Final Engineering Design Proposal 65-11-22
4920
Owner/Contractor contract documents (except technical documents) and/or
purchase order, in order to solicit for and enter into a construction contract with a
Contractor or Construction Manager.
Solicit, administer, and award bids for construction implementation of this project.
Provide construction administration and supervisions of Contractor or Construction
Manager.
ITEMS NOT INCLUDED
1. More meetings than identified in basic and additional services.
2. Construction drawings and specifications. (Note: At this time the City has not
defined the scope or method of project delivery, or its phasing, which would dictate
the criteria of scope and extent of these construction documents). Segments 3, 4, 6
& 11-14 all other drawings and specs.
3, Changes to the final engineering designs that are a result of issued state, federal or
city permit conditions.
A.i Geotechnical Analyses & Recommendations
TTG intends to subcontract the geotechnical engineering work to SLR International
(formerly HTE Northeast, Inc.} out of Bedford, NH. TTG has performed many similar
water/land projects with SLR support.
13.7
13.8
13.9
13.10
Design the new floating dock and gangway system including intermediate supports.
Re-examine the “0.00 ft rise” river model with the final design pile features to
confirm conformance.
Use the river model to assess pile erosion and scour, ice, and woody/miscellaneous
debris loadings.
Prepare final design drawings and specifications for City review and approval.
Segment 14 — Renaissance Park Improvements
14.1
14.2
14.3
14.4
14.5