Finance Committee - Agenda - 10/2/2019 - P91
Lighting Change
Scope: Remove and replace lighting in Generator room per attached El! quote.
Lighting Change
Scope: Remove and replace lighting in Generator room per attached El! quote.
Industral Doc #: PCO NO 005
a a Ref. Document:
PROJECT NAME: Energy Recovery Upgrade IFB0501- Date: 26-Aug-19
090618
PROJECT NO: 181012
PHASE
COST SUMMARY SHEET
Lighting Change
A McC Labor (Recap Sheet): $0.00
B MC Materials, & Equipment (Recap Sheet): $0.00
Cc MIG Fee (A x 15%) + (B x 10%): $0.00
D Subtotal MC Work (A+B+C): | $ -
E Total Subcontractors (Below): $3,737.50
F MC Mark-up on Subcontractor Work (5%): | $ 186.88
G Bond (1%) and General Liability (1%): $78.49
WALDRON ENGINEERING &
JL Ge
CONSTRUCTION, NG.
To: William Keating, P.E., Project Engineer, Nashua Wastewater Treatment Facility
From: Erich Gustenhoven, P.E., Resident Engineer, Waldron Engineering &
Construction, Inc.
Date: September 17,2019
Re: Change Order Request Review 005&006
NWWYTE Energy Recovery Upgrade Project
Attachments: Methuen Construction PCO #005-Lighting
Methuen Construction PCO #006-Painting
Mr. Keating:
CHANGE ORDER
No. 2
PROJECT: Energy Recovery Upgrade
OWNER: City of Nashua, NH
229 Main Street, Nashua, NH
(Address)
CONTRACTOR: Methuen Construction
CONTRACT
FOR: Energy Recovery Upgrade
DATE OF ISSUANCE: 09/17/19
OWNER’s Project No. _IFB0501-091618
ENGINEER Waldron Eng. & Const., Inc.
ENGINEER’s Project No. 359.01
You are directed to make the following changes in the Contract Documents.
Description:
Purpose of Change Order:
Justification:
ARTHUR COLE PAINTING CORPORATION
Contract Painting
Specialty Coatings
Wallcoverings
Millwork Finishing
Maintenance Programs
Mechanical Room Painting
Scope: The below price is the cost incurred to paint Mechanical room, including power washing ceilings, walls, floor and filling unused holes with mortar.
Mechanical Room Painting
Scope: The below price is the cost incurred to paint Mechanical room, including power washing ceilings, wails, floor and filing unused holes with mortar.
Doc #: 6
Ref. Document:
PROJECT NAME: Date: 4-Sep-19
Nashua Energy Recovery Upgrade
PROJECT NO: 181012
PHASE
COST SUMMARY SHEET
Mechanical Room Painting
A Mc Labor (Recap Sheet): $4,282.10
B MC Materials, & Equipment (Recap Sheet): $453.00
Cc MC Fee (A x 15%) + (B x 10%): $687.62
D Subtotal MC Work (A + B+): | $ 5,422.72
E Total Subcontractors (Below): $10,875.00
F MG Mark-up on Subcontractor Work (5%): | $ 543.75
G Bond (1%) and General Liability (1%): $336.83
DR-UNV-
L835-CD1-WL-U
Light Fixtures
006 *EP*-Entire Project | Conduit Parts Material $175.00 1.00 -| $175.00
Breakout
Labor : $7,575.00
Gross Margin Percent @ 15%: $236.25
Material : $1,675.00
Gross Margin Percent @ 15%: $251.25
Total: $3,737.50
Reservation of Rights
This price does not include any amount for impacts such as interference, disruptions, rescheduling, changes in the
sequence of work, delays and/or associated acceleration. We expressly reserve the right to submit our request for
Electrical
. Installations, Inc.
Enginvering -Construction-Cantral Systems
snsctisumanneehenters NH
MAIN OFFICE
397 Whittier Highway
Moultonboro, NH 03254
603-253-4525
FAX 603-253-6284
BRANCH OFFICE
9308 American Legion Hwy
Westport, MA 02790
508-636-8600
FAX 508-636-8650
VT License EM-2667 ME License 7908 NHLicense 460 MA License 221MR
Potential 004
1929 — Nashua, NH - WWTF Engergy Recovery
Subject: 10 LED 4' Vapor tight lights in generator