Industral Doc #: PCO NO 005
a a Ref. Document:
PROJECT NAME: Energy Recovery Upgrade IFB0501- Date: 26-Aug-19
090618
PROJECT NO: 181012
PHASE
COST SUMMARY SHEET
Lighting Change
A McC Labor (Recap Sheet): $0.00
B MC Materials, & Equipment (Recap Sheet): $0.00
Cc MIG Fee (A x 15%) + (B x 10%): $0.00
D Subtotal MC Work (A+B+C): | $ -
E Total Subcontractors (Below): $3,737.50
F MC Mark-up on Subcontractor Work (5%): | $ 186.88
G Bond (1%) and General Liability (1%): $78.49
Total Proposal (D+#E+F+G): § 4,002.86
SUBCONTRACTOR SUMMARY
Description
Lighting Change
Amount
3,737.50
$
$
$
g -
g -
g -
$
$
Total Subcontractors: 3,737.50