Finance Committee - Agenda - 10/2/2019 - P88

By dnadmin on Mon, 11/07/2022 - 13:03
Document Date
Fri, 09/27/2019 - 12:02
Meeting Description
Finance Committee
Document Type
Agenda
Meeting Date
Wed, 10/02/2019 - 00:00
Page Number
88
Image URL
https://nashuameetingsstorage.blob.core.windows.net/nm-docs-pages/fin_a__100220…

CHANGE ORDER

No. 2

PROJECT: Energy Recovery Upgrade

OWNER: City of Nashua, NH

229 Main Street, Nashua, NH

(Address)
CONTRACTOR: Methuen Construction

CONTRACT
FOR: Energy Recovery Upgrade

DATE OF ISSUANCE: 09/17/19

OWNER’s Project No. _IFB0501-091618

ENGINEER Waldron Eng. & Const., Inc.

ENGINEER’s Project No. 359.01

You are directed to make the following changes in the Contract Documents.

Description:
Purpose of Change Order:
Justification:

Attachments: (List documents supporting change)

CHANGE IN CONTRACT PRICE

Original Contract Price
$ _1,787,378.00

CHANGE IN CONTRACT TIME

Original Contract Time
280 (Final Completion)

(days or date}

Previous Change Orders
$ _ 16,742.40

Net change from previous Change Orders
none

{days}

Contract Price prior to this Change Order
$ _1,804,120.40

Contract Time prior to this Change Order

280 (Final Completion)
(days or date)

Net Increase (Decrease) of this Change Order
$ 21,181.16

Net Increase (decrease) this Change Order

none
{days}

Contract Price with all approved Change Orders
$ _ 1,825,301.56,

Contract Time with all Change Orders
280 (Final Completion)

(days or date)

This document will become a supplement to the CONTRACT and all provisions will apply hereto. The
attached Contractor’s Revised Project Schedule reflects increases or decreases in Contract Time as
authorized by this Change Order.

Stipulated price and time adjustment includes all costs and time associated with the above described
change. Contractor waives all rights for additional time extension for said change. Contractor and Owner
agree that the price(s) and time adjustment(s) stated above are equitable and acceptable to both parties.

RECOMMENDED: APPROVED: APPROVED: APPROVED:
By: By: By: By:

Engineer Owner Contractor NHDES

Date Date Date Date