Finance Committee - Agenda - 9/4/2019 - P85
Hazen
SCOPE OF WORK.
CSO LONG TERM CONTROL PLAN UDPATE / INTEGRATED PLAN
GENERAL
Hazen
SCOPE OF WORK.
CSO LONG TERM CONTROL PLAN UDPATE / INTEGRATED PLAN
GENERAL
SUMMARY OF LABOR AND COSTS
CITY OF NASHUA, NH
CSO Long-Term Control Plan Update / integrated Plan
HAZEN AND SAWYER TEAM BUDGET
Notes:
1) Assumes 7 flow meters for 12 waaks (Flow Assessment quote, August 13, 2019)
2) Exclucies receiving water quality modeling/monitoring
3) Assumes 21 months total project duration
4) Asoumes 11 meatings total (Inclu
ig EPA quarterly updates)
wastewater collection system since 1997 and rehabilitation work including
replacing and lining of sewers in portions of the City.
Te:
From
Re:
C, Motion:
Attachments:
Discussion:
City of Nashua, Public Works Division
Board of Public Works Meeting Date: August 22, 2019
Stephen Dockran, P.E., City Engineer
Engineering Department
Consent Decree
2019 Updated Long Term Control Plan
THE CITY OF NASHUA “the Gate City’
Administrative Services
Purchasing Department
August 29, 2019
Memo #20-025
TO: MAYOR DONCHESS
FINANCE COMMITTEE
SUBJECT: CONSENT DECREE — 2019 UPDATED LONG TERM CONTROL PLAN (VALUE: NOT-
TO EXCEED $487,760)
DEPARTMENT: 169 WASTEWATER; FUND: WASTEWATER
Please see the attached communication from Stephen Dookran, P.E., City Engineer, dated August 22,
2019 for information related to this contract.
To:
From:
Re:
B. Motion:
Discussion:
City of Nashua, Public Works Division
Board of Public Works Meeting Date: August 22, 2019
Stephen Dookran, P.E., City Engineer
Engineering Department
Monica Drive Drainage Improvements
To approve a contract for Monica Drive Drainage Improvement Project with RWC
Enterprise for the amount not to exceed $129,900. Funding will be through
Department: 169 Wastewater, Fund: Wastewater; Activity: Stormwater Abatement.
THE CITY OF NASHUA “The Gate City’
Aldnuinistrative Services
Purchasing Department
August 29, 2019
Memo #20-024
TO: MAYOR DONCHESS
FINANCE COMMITTEE
SUBJECT: MONICA DRIVE DRAINAGE IMPROVEMENTS (VALUE: $129,900)
DEPARTMENT: 169 WASTEWATER; FUND: WASTEWATER
Please see the attached communication from Stephen Dookran, P.E., City Engineer, dated August 22,
2019 for information related to this contract.
Summary
CHANGE IN CONTRACT PRICE:
Original Contract Price
$35,000
CHANGE IN CONTRACT TIMES:
Original Contract Times
Substantial completion: N/A
Ready for final payment: N/A
Net changes from previous Change Orders
$9,550
Net change from previous Change Orders
NONE
Contract Price prior to this Change Order
$44,550
Contract Times prior to this Change Order
Substantial completion: N/A
Ready for final payment: N/A
Net Increase {decrease} of this Change Order
$20,000
CHANGE ORDER
No. 2
PROJECT: Marshall Street Drainage Improvements
OWNER’S CONTRACT NO: N/A
EXECUTED CONTRACT DATE: June 13, 2018
DATE OF ISSUANCE: September 5, 2019 EFFECTIVE DATE: Upon City Approval
OWNER: City of Nashua, NH
OWNER’s Purchase Order NO.: 141603
CONTRACTOR: Thibeault Corporation of NE
ENGINEER: DPW Engineering
You are directed to make the following changes in the Contract Documents:
Description:
To make additional grading and drainage improvements, at 22 Marshall Street, that
To:
From:
Re:
KE. Motion:
Discussion:
City of Nashua, Public Works Division
Board of Public Works Meeting Date: August 22, 2019
Stephen Dookran, P.E., City Engineer
Engineering Department
Marshall Street Roadway Improvements
To approve change order #2 with Thibeault Corporation of Manchester, NH for the
amount not to exceed $20,000 for roadway improvements on Marshall Street. Funding
will be through Department: 169 Wastewater; Fund: Wastewater; Activity: CSO
Flooding.