CHANGE ORDER
No. 2
PROJECT: Marshall Street Drainage Improvements
OWNER’S CONTRACT NO: N/A
EXECUTED CONTRACT DATE: June 13, 2018
DATE OF ISSUANCE: September 5, 2019 EFFECTIVE DATE: Upon City Approval
OWNER: City of Nashua, NH
OWNER’s Purchase Order NO.: 141603
CONTRACTOR: Thibeault Corporation of NE
ENGINEER: DPW Engineering
You are directed to make the following changes in the Contract Documents:
Description:
To make additional grading and drainage improvements, at 22 Marshall Street, that
includes removing t crumbling concrete road base and replacing with new gravel.
Change Order #2 1 of 2