City of Nashua, Public Works Division
Board of Public Works Meeting Date: August 22, 2019
Stephen Dookran, P.E., City Engineer
Engineering Department
Marshall Street Roadway Improvements
To approve change order #2 with Thibeault Corporation of Manchester, NH for the
amount not to exceed $20,000 for roadway improvements on Marshall Street. Funding
will be through Department: 169 Wastewater; Fund: Wastewater; Activity: CSO
Flooding.
Currently, road and drainage work on Marshall St is being performed by Thibeault
Corporation in relation to the new housing development at 22 Marshall Street. DPW
would like to make additional grading and drainage improvements to this section of
Marshall St that include removing the crambling concrete road base and replacing it
with new gravel.
Using Thibeault to do the additional roadway work is the best option while they are
already mobilized for that type of work. The residents of this section of Marshall St
have endured poor pavement and drainage conditions for years. With the new
development being built, now is the time to rectify these problems. Thibeault has
already performed additional drainage work for the city in a satisfactory manner.
The original contract with Thibeault was in the amount of $35,000 with Change Order
#1 adding $9,550. With Change Order #2 the contract value will increase to $64,550.
The mulling and paving of Marshall St will be done under the city’s 2019 paving
program.