Finance Committee - Agenda - 9/5/2018 - P208

By dnadmin on Mon, 11/07/2022 - 11:29
  • Read more about Finance Committee - Agenda - 9/5/2018 - P208

City of Nashua, NH Page 3
Bid for Design/Build — Fuel Island Upgrade August 1, 2018

8. Pricing for Installation of Fuel Dispenser and Pans based on installing four (4) new
dispensers. Unit pricing subject to change if less than four (4) installed.

9. Inspection of ASTs will require the tanks to be emptied and cleaned. Bid includes the
removal and disposal of up to 95 gallons of residual product from each tank. Bid does not
include the transportation and disposal of any tank solids or sludge.

Finance Committee - Agenda - 9/5/2018 - P207

By dnadmin on Mon, 11/07/2022 - 11:29
  • Read more about Finance Committee - Agenda - 9/5/2018 - P207

City of Nashua, NH Page 2
Bid for Design/Build — Fuel Island Upgrade August 1, 2018

Finance Committee - Agenda - 9/5/2018 - P206

By dnadmin on Mon, 11/07/2022 - 11:29
  • Read more about Finance Committee - Agenda - 9/5/2018 - P206

a
Envi rolrac EXHIBIT B

Environmental Services
August 1, 2018

City of Nashua via Bid Express
Central Purchasing Office

229 Main Street

Room 128

Nashua, NH 03061

Attn: Danielle Greenberg
Purchasing Agent Il

Re: Bid for Design/Build — Fuel Island Upgrade
IFB0465-080118

Dear Ms. Greenberg:

Finance Committee - Agenda - 9/5/2018 - P205

By dnadmin on Mon, 11/07/2022 - 11:29
  • Read more about Finance Committee - Agenda - 9/5/2018 - P205

EXHIBIT A
IFBO0465-020118
Design/Build - Fuel Island Upgrade

INSTALLATION OF FIRE SUPRESSION

> Re-install existing Emergency Shut down button per NFPA 30A Section 6.7.
> Canopy shall have an approved Automatic Fire Suppression System installed to meet the
requirements of NFPA 30A Section 7.3.5.1 & 7.3.5.2.

INSTALLATION OF CANOPY
(excluding excavation and installation of canopy bases)

Finance Committee - Agenda - 9/5/2018 - P204

By dnadmin on Mon, 11/07/2022 - 11:29
  • Read more about Finance Committee - Agenda - 9/5/2018 - P204

EXHIBIT A
iFB0465-080118
Design/Build - Fuel Island Upgrade

CONTRACTOR SCOPE OF WORK

CONTRACTOR shall prepare design plans for the construction of a new Fuel Island Upgrade .The design
plans shall meet the following requirements:

>
>

>

Plans to be prepared by a licensed State of New Hampshire Professional Engineer.
Plans must conform to State Environmental Regulations and be approved by the New
Hampshire Division of Environmental Services (NH-DES).

Finance Committee - Agenda - 9/5/2018 - P203

By dnadmin on Mon, 11/07/2022 - 11:29
  • Read more about Finance Committee - Agenda - 9/5/2018 - P203

IN WITNESS WHEREOF, the parties hereto have caused this contract to be signed and intend to be
legally bound thereby.

City of Nashua, NH (signature) Envirotrac Environmental Services Ltd.
(signature)

James Donchess, Mayor
(Printed Name and Title) (Printed Name and Title)

Date Date

Page 12 of 12

Finance Committee - Agenda - 9/5/2018 - P202

By dnadmin on Mon, 11/07/2022 - 11:29
  • Read more about Finance Committee - Agenda - 9/5/2018 - P202

ARTICLE 16— DISPUTE RESOLUTION

Finance Committee - Agenda - 9/5/2018 - P201

By dnadmin on Mon, 11/07/2022 - 11:29
  • Read more about Finance Committee - Agenda - 9/5/2018 - P201

Upon receipt of notice of termination for cause, CONTRACTOR shall:

1. Immediately discontinue WORK on the date and to the extent specified in the notice.

2. Provide the OWNER with a list of all unperformed services.

Place no further orders or sub-contracts for materials, services, or facilities, other than as

may be necessary or required for completion of such portion of WORK under the contract

that is not terminated.

Finance Committee - Agenda - 9/5/2018 - P200

By dnadmin on Mon, 11/07/2022 - 11:29
  • Read more about Finance Committee - Agenda - 9/5/2018 - P200

conflict exists and was not disclosed to the OWNER, it may terminate the contract at will or for
cause.

ARTICLE 15 — TERMINATION OF THE CONTRACT
TERMINATION, ABANDONMENT, OR SUSPENSION AT WILL

Finance Committee - Agenda - 9/5/2018 - P199

By dnadmin on Mon, 11/07/2022 - 11:29
  • Read more about Finance Committee - Agenda - 9/5/2018 - P199

9. Substantial completion is the stage in the progress of the WORK when the WORK or
designated portion thereof is sufficiently complete in accordance with the Contract
Documents so the OWNER can occupy or utilize the WORK for its intended use.