Skip to main content

Main navigation

  • Documents
  • Search

User account menu

  • Log in
Home
Nashua City Data

Breadcrumb

  1. Home
  2. Finance Committee - Agenda - 9/5/2018 - P205

Finance Committee - Agenda - 9/5/2018 - P205

By dnadmin on Mon, 11/07/2022 - 11:29
Document Date
Fri, 08/31/2018 - 12:49
Meeting Description
Finance Committee
Document Type
Agenda
Meeting Date
Wed, 09/05/2018 - 00:00
Page Number
205
Image URL
https://nashuameetingsstorage.blob.core.windows.net/nm-docs-pages/fin_a__090520…

EXHIBIT A
IFBO0465-020118
Design/Build - Fuel Island Upgrade

INSTALLATION OF FIRE SUPRESSION

> Re-install existing Emergency Shut down button per NFPA 30A Section 6.7.
> Canopy shall have an approved Automatic Fire Suppression System installed to meet the
requirements of NFPA 30A Section 7.3.5.1 & 7.3.5.2.

INSTALLATION OF CANOPY
(excluding excavation and installation of canopy bases)

> Install a two (2) column fuel island canopy with 16’ clearance equipped with 6-8 LED light
fixtures.
> Install bollards at either end of the fuel island.

INSPECTION OF FUEL STORAGE TANKS

> The above ground storage tanks are due for the required 20 year internal inspection per NH
DES. The tank inspections shall be done to coincide with the fuel island project.

GENERAL REQUIREMENTS

» ICC certified personnel to be on site for installation and State of NH inspections

> Shall submit, before project acceptance, all Manufacturer manuals, warranty registrations, and
Operating procedures for operating, maintaining, and troubleshooting for new fuel dispensers
(if not provided by Manufacturer).

CITY of NASHUA’S SCOPE OF WORK

> The City will provide any and all excavation, demo, and disposal of existing infrastructure.
>» The City will excavate for and install two (2) concrete canopy bases.
> The City will perform all flat work (concrete and asphalt).