The method of adjusting these castings shall be as follows: Cut around catch basin or
manhole castings a minimum of 8-inches from casting. Excavate and if required rebuild up to
12-inches of masonry below the bottom of the casting. Backfill with suitable material and
compact to bottom of casting. Place high, early strength cement or bituminous
concrete collar, as directed, to approximately 1 '/2-inches below the raised casting grade.
Masonry work shall conform to Section 02631, PRECAST MANHOLES AND CATCH
BASINS.
In some areas, raising of castings may not be required. Where directed by the Engineer,
castings not to be raised shall have at least 12-inches of bituminous concrete pavement
chipped and removed around the casting. New bituminous concrete pavement shall be
placed and compacted around such castings to approximately 1-1/2-inches below the top of
the casting. The overlay course shall then be sloped down to the level of the casting.
The method of raising valve boxes shall be as follows: Cut around valve box a minimum of
8-inches from valve box. Excavate as required and raise the valve box. Pour high early
strength cement or bituminous concrete collar, as directed, to approximately 1-1/2-inches
below the top of the valve box.
Castings which need to be raised or adjusted to complete permanent curb to curb paving
shall be done immediately prior to paving.
PAVEMENT MARKINGS:
The Contractor shall replace all pavement markings removed or covered-over in carrying out
the work, and as directed by the Engineer, no sooner than 48 hours after completion of
permanent pavement. The markings and respective mixture and application requirements
shall conform to the requirements of NHDOT Standard Specifications Section 632.
When directed by the Engineer, the Contractor shall provide temporary markings at no
additional cost to the Owner.
PAVEMENT REPAIR:
If required in the contract or if permanent pavement becomes rough or uneven, permanent
pavement patches and trenches shall be repaired and brought to grade utilizing "infrared"
paving methods following completion of the construction.
The Contractor performing the work shall use care to avoid overheating the pavement
being repaired.
Pavement repair shall extend a minimum of 6-inches beyond all edges of the pavement
patch to assure adequate bonding at the pavement joints.
END OF SECTION