Finance Committee - Agenda - 3/17/2021 - P527

By dnadmin on Mon, 11/07/2022 - 13:46
  • Read more about Finance Committee - Agenda - 3/17/2021 - P527

SECTION 02200

EARTHWORK

PART 1 - GENERAL

11 SCOPE OF WORK

A.

CONTRACTOR shall provide all labor, materials, equipment, and incidentals
necessary to excavate and backfill trenches for the landfill gas collection and
control system as shown on the Drawings and specified herein, including, but
not limited to: excavation, disposal, and/or replacement of waste; placement
and compaction of earth materials; and grading.

PART 2 - PRODUCTS

2.1 GENERAL

A.

Finance Committee - Agenda - 3/17/2021 - P526

By dnadmin on Mon, 11/07/2022 - 13:46
  • Read more about Finance Committee - Agenda - 3/17/2021 - P526

CONTENTS

DIVISION 2 - SITE WORK

Section 02200 - Earthwork

Section 02275 — Nonwoven Geotextile

Section 02350 - Odor Control During Construction
Section 02550 - Gcomembrane

Section 02560 — LFG Extraction Wells

P:\3000s\3 066.2 1\Source Files\Tech Specs\ Division 2 Specifications\ 00000 Divison 2 Table of Contents.docx

SANBORN {| HEAD

Finance Committee - Agenda - 3/17/2021 - P525

By dnadmin on Mon, 11/07/2022 - 13:46
  • Read more about Finance Committee - Agenda - 3/17/2021 - P525

Section 01780 — Project Record Documents Page 2 of 2
January 2021 3066.21

PART 3 - EXECUTION

Not used.

[END OF SECTION 01780]

P:\3000s\3066.21\Source Files\Tech Specs\Division 1 Specifications\01780 Record.docx

SANBORN \ HEAD

Finance Committee - Agenda - 3/17/2021 - P524

By dnadmin on Mon, 11/07/2022 - 13:46
  • Read more about Finance Committee - Agenda - 3/17/2021 - P524

SECTION 01780

PROJECT RECORD DOCUMENTS

PART 1 - GENERAL

1.1 MAINTENANCE OF PROJECT RECORD DOCUMENTS AND SAMPLES

A.

B.

CONTRACTOR shall document the construction using red-lined drawings.

CONTRACTOR shall maintain at the site for OWNER’s permanent record one
complete set of project documents that includes a copy of the: Drawings, red-
lined drawings, Specifications, Addenda, Change Orders, Submittals and Shop
Drawings, quality control field reports, product data, equipment manuals, and
material samples.

Finance Committee - Agenda - 3/17/2021 - P523

By dnadmin on Mon, 11/07/2022 - 13:46
  • Read more about Finance Committee - Agenda - 3/17/2021 - P523

Section 01520 - Construction Facilities and Temporary Controls Page 2 of 2
January 2021 3066.21

1.4 REMOVAL OF UTILITIES, FACILITIES AND CONTROLS
A. CONTRACTOR shall remove temporary facilities, equipment, and materials that
CONTRACTOR installed during the performance of the Contract Work.
CONTRACTOR shall restore existing and permanent facilities used during the
performance of Work to original or better condition.
PART 2 - PRODUCTS
Not used.

PART 3 - EXECUTION

Not used.

[END OF SECTION 01520]

Finance Committee - Agenda - 3/17/2021 - P522

By dnadmin on Mon, 11/07/2022 - 13:46
  • Read more about Finance Committee - Agenda - 3/17/2021 - P522

SECTION 01520

CONSTRUCTION FACILITIES AND TEMPORARY CONTROLS

PART 1 - GENERAL

1.1

1.2

1.3

SUMMARY

A.

CONTRACTOR shall maintain areas outside the limits of work free of waste
materials, debris, and rubbish that are a direct result of work performed by
CONTRACTOR.

TEMPORARY UTILITIES

A.

CONTRACTOR shall provide drinking water for his employees, ENGINEER, and
OWNER’s representatives.

CONTRACTOR shall provide portable sanitary facilities for use by all project
personnel.

Finance Committee - Agenda - 3/17/2021 - P521

By dnadmin on Mon, 11/07/2022 - 13:46
  • Read more about Finance Committee - Agenda - 3/17/2021 - P521

Section 01450 - Quality Control Page 2 of 2

January 2021

3066.21

made, if desired, for observation before shipment from the place of
manufacture. CONTRACTOR must anticipate that possible delays may occur
due to the necessity of materials being inspected and accepted for use.

1.3 SUBSTANDARD WORK OR MATERIALS

A.

Finance Committee - Agenda - 3/17/2021 - P520

By dnadmin on Mon, 11/07/2022 - 13:46
  • Read more about Finance Committee - Agenda - 3/17/2021 - P520

SECTION 01450

QUALITY CONTROL

PART 1 - GENERAL

1.1 GENERAL QUALITY CONTROL

A.

CONTRACTOR - shall maintain quality control over the _ suppliers,
manufacturers, products, services, site conditions, and workmanship to
produce Work of specified quality.

CONTRACTOR shall comply with industry standards except when more
restrictive tolerances or specified requirements indicate more rigid standards
or more precise workmanship.

Finance Committee - Agenda - 3/17/2021 - P519

By dnadmin on Mon, 11/07/2022 - 13:46
  • Read more about Finance Committee - Agenda - 3/17/2021 - P519

Section 01330 - Submittals Page 4 of 4
January 2021 3066.21

7. Applicable standards, such as ASTM or Federal Specification numbers;
8. Identification of deviations from Contract Documents; and
9. Identification of revisions on resubmittals.

19 RESUBMISSION REQUIREMENTS

A. CONTRACTOR shall make any and all corrections or changes in submittals
required by ENGINEER, and resubmit revised versions. Submittals shall not be
accepted until ENGINEER reviews and approves of revised versions.

Finance Committee - Agenda - 3/17/2021 - P518

By dnadmin on Mon, 11/07/2022 - 13:46
  • Read more about Finance Committee - Agenda - 3/17/2021 - P518

Section 01330 - Submittals Page 3 of 4
January 2021 3066.21
B. CONTRACTOR shall complete all of the following items no later than the

specified number of calendar days.

Associated shipping, work, and use of

materials by CONTRACTOR shall not begin until ENGINEER’s review of each
respective submittal is complete and where resubmission by CONTRACTOR is
not required by ENGINEER. ENGINEER shall reply to CONTRACTOR within 7
calendar days of receipt of each submittal and state whether or not

CONTRACTOR must resubmit.